background image

8

Air Handling Unit

Installation, Operation, and Maintenance Manual

April 2021

6.2 Assembling Unit Sections

1. 

Place unit sections as close to their final 

installation position as possible, making sure 

all sections are correctly oriented to mating 

sections. Serial numbers for each section will 

be on the same side and in order, SNXXXXX-1, 

SNXXXXX-2, etc., continuing for all sections of 

unit.

2.  Remove bolts along unit split planes on wall and 

roof panels. Remove shipping lugs if installed 

between unit sections. Remove plastic covering 

the unit split opening.

3.  Install panel joint gasket, ClimateCraft part 

number PGSK-001-001 along base frame tube. 

Two pieces of gasket material should be used 

as shown in Figure 6-5. The first piece of gasket 

should be at floor level with wide portion of 

“T” gasket close to top of base rail following its 

radius. The second piece should be inverted and 

close to the center of the tube. Both pieces of 

gasket need to be installed using the double-

sided tape provided in loose parts box inside 

unit. Gasket material should extend beyond 

edges of each section. Gasket installation must 

be done before sections are pulled together.

4.  Install panel joint gasket, ClimateCraft part 

number PGSK-001-001, on wall and roof panel 

flanges. If the sections are level, plumb and at 

the same height, all wall panel and roof panel 

bolt holes should be aligned. If they are not, 

the condition preventing alignment must be 

corrected prior to pulling the sections together. 

See Section 6.1 above.

5.  Maneuver unit sections into final position.  

Ensure base frames are as close as possible 

(touching) while maintaining hole alignment.

6.  Draw unit sections together using section split 

assembly hardware. DO NOT ATTEMPT TO 

DRAW THE SECTIONS TOGETHER USING THE 

PANEL BOLTS.

7.  Check unit for proper alignment prior to bolting 

of wall panels and roof sections. If unit is not 

square and plumb it is possible for air/water 

leaks to occur. Proper alignment of roof rails can 

be seen at the section joints, roof rails should 

be almost touching and flush together if unit is 

level, square and plumb.

8.  Once the sections are together, insert panel 

bolts and nuts along roof and wall panels. 

Tighten bolts and nuts securely.

9.  After verifying unit section bases are touching 

along unit split planes, caulk joint between 

adjacent base frame sections and at end seam 

of roof panel joints of unit.

10. Units that are wider than 12 feet and/or have 

a steel roof frame instead of aluminum require 

caulk along the roof rail at the point both 

sections of the unit come together.

11. For outdoor units, the roof seam cover caps 

must be installed. Do not seal seam-cover end 

caps as this will prevent rainwater from draining 

off roof.

6.3 Component Clearances

Because ClimateCraft, Inc. specializes in the 

manufacture of custom products, it is difficult to 

generalize about product clearances. However, certain 

minimum clearances should be observed to facilitate 

access to the unit and major components.

•  Access Doors – The area around an access door 

should be clear to allow the door to swing fully 

open without obstruction.

•  Coils & Major Components – In order to 

allow for replacement of coils and other 

major components, the area adjacent to the 

component should be clear an equivalent of the 

width of the component, plus an additional 5 

feet to allow for equipment access.

Maintaining clearances around the air handling unit 

required for local, state, and national codes is the 

responsibility of the licensed installing contractor.

NOTICE

Summary of Contents for DHII-007

Page 1: ...Factory Assembled Custom Air Handling Units Installation Operation and Maintenance Manual April 2021 IOM SL E 041521 AHU Indoor Custom AHU Outdoor Custom AHU...

Page 2: ...d to the equipment Table of Contents SECTION DESCRIPTION PAGE 1 0 General 3 2 0 Receiving 3 3 0 Storage 3 4 0 Roof Curb Installation 4 5 0 Rigging 5 6 0 Unit Assembly 7 7 0 Condensate Drain 12 8 0 Fil...

Page 3: ...ClimateCraft air handling units are factory inspected prior to shipment Digital photos are taken of the unit and loose parts These photos are available for review by calling ClimateCraft Please verif...

Page 4: ...an 1 8 over the entire air handling unit Curb gasket must be placed between the curb and the air handling unit Curb gasket provides an air seal between the unit and the curb A sealant may be used in p...

Page 5: ...delivered fully assembled or in sections requiring on site assembly In either case each section will have a minimum of 4 lifting lugs bolted or welded to the unit base frame Spreader bars are required...

Page 6: ...6 Air Handling Unit Installation Operation and Maintenance Manual April 2021 Figure 5 1 Example of proper rigging and lifting Figure 5 2 Example of proper rigging and lifting...

Page 7: ...the unit is not properly aligned after rigging placement it must be square and plumb prior to section assembly NOTICE Figure 6 1 Unit base frames properly aligned gasketed and joined Figure 6 2 Unit p...

Page 8: ...ions together using section split assembly hardware DO NOT ATTEMPT TO DRAW THE SECTIONS TOGETHER USING THE PANEL BOLTS 7 Check unit for proper alignment prior to bolting of wall panels and roof sectio...

Page 9: ...9 We make air handling technology Better Air Handling Unit Installation Operation and Maintenance Manual April 2021 Figure 6 5 Figure 6 6...

Page 10: ...10 Air Handling Unit Installation Operation and Maintenance Manual April 2021 Figure 6 7 Figure 6 8...

Page 11: ...se frame of vestibule as shown in Figure 6 9 2 Affix a single layer of PGSK 001 001 to the roof panel flange of vestibule Figure 6 10 3 Affix using double sided tape gasket PGSK 005 003 to the wall pa...

Page 12: ...f the cooling coil is in a draw through application Static pressure will not allow the drain pan to empty if a properly plumbed trap is not used Cooling coils and drain pans in a blow through or posit...

Page 13: ...ive Internal Static Pressure in Drain Pan Section in w g 1 H 2 Negative Internal Static Pressure in Drain Pan Section in wg divided by 2 Example Neg SP in Drain Pan Section 3 6 in w g H 3 6 1 4 6 H 2...

Page 14: ...pt clean 8 1 Slide Type Filter Rack This filter rack uses horizontal channels into which the filters slide Filters are loaded in the frame through a removable end or on the side where a portion of the...

Page 15: ...otation of the adjusting nut compresses the spring and raises the fan while clockwise rotation of the adjusting nut lowers the fan Begin the adjusting process at the heaviest corner of the fan and pro...

Page 16: ...ith opening sleeve 4 Secure rainhood to opening sleeve with sheet metal screws provided assuring continuous seal between gasket and rainhood Figure 10 1 10 2 Stacked Rainhoods Prior to installation st...

Page 17: ...tential for belt failure and possibly quiet the unit A ClimateCraft startup form is available for recording startup conditions by contacting ClimateCraft Service by email at support climatecraft com 1...

Page 18: ...eave has a small notch on the O D of the flange This mark is located directly over the keyway on the two adjustable flanges and over one of the keyways on the non adjustable center flange To obtain pr...

Page 19: ...n bolts Use the motor adjustment screws to achieve proper deflection and re tighten when deflection requirements are satisfied Belts become seated in pulley grooves after a period of operation usually...

Page 20: ...RPM Bearing Bore inches 1 2 1 1 1 8 1 1 2 1 5 8 1 7 8 1 15 16 2 3 16 2 7 16 3 3 3 16 3 1 2 3 15 16 4 1 2 4 15 16 5 1 2 To 250 12 12 12 12 12 12 10 9 500 12 12 10 10 8 7 5 5 720 12 9 8 7 6 4 3 3 1000...

Page 21: ...not visible to observe purged grease lubricate with number of shots indicated for bore size Consult factory for lubrication intervals under severe operating conditions such as high temperatures moist...

Page 22: ...d and maintained Please use the following guidelines to build your FanMatrix maintenance program Recommended Grease Polyrex EM Mobil Compatible Greases Texaco Polystar Rykon Premium 2 Penzoil Pen 2 Lu...

Page 23: ...to Add in oz gm Volume of Grease to Add in3 Teaspoons 56 to 140 6203 0 08 2 4 0 15 0 5 140 6205 0 15 3 9 0 20 0 8 180 6206 0 19 5 0 0 30 1 0 210 6307 0 30 8 4 0 60 2 0 250 6309 0 47 12 5 0 70 2 5 280...

Page 24: ...ired a 1 8 Allen Wrench tool shown in photo To tighten the door handles use two 9 16 wrenches On inward opening doors a T 27 is needed to adjust the location of the roller cam Using the same T 27 to t...

Page 25: ...ectrical Wiring Determine size and location of penetration from outside of air handling unit Drill then hole saw desired hole in proper location first from outside of unit Repeat process on interior s...

Page 26: ...oupling into panel from outside of unit with appropriately sized nipple Slide reducing washer over nipple and attach a second wall coupling to nipple Attach connector to wall coupling from inside unit...

Page 27: ...ant for contaminant induced friction causing excessive lubricant evaporation Purge system per this manual and replace with fresh lubricant Cleaning bearings may be necessary Make sure bearings are sec...

Page 28: ...talled Inspect cut off installation and install per vendor instructions Fan inlet obstruction Re sheave fan motor to increase fan speed Correct obstructions Impeller not centered on inlet collar Adjus...

Page 29: ...teCraft air handling unit resulting from operation in surge it not covered by the ClimateCraft Limited Warranty The fans also produce excessive noise and the pressure pulsations can produce objectiona...

Page 30: ...1 028 1 047 1000 0 999 1 018 1 037 1 056 1500 1 008 1 027 1 047 1 066 2000 1 017 1 037 1 056 1 076 2500 1 027 1 047 1 066 1 085 3000 1 036 1 056 1 076 1 095 3500 1 045 1 066 1 086 1 105 4000 1 055 1...

Page 31: ...e down or up arrow key until the display matches the K factor for your appli cation as listed above Now hit the enter key once to save this setting The display should stop blinking Hit the down arrow...

Page 32: ...ty ft sec GPM 0 41 tube diameter 2 Pump hp GPM ft head 3960 efficiency Steam lb hr CFM T2 T1 1000 Total Heat 4 5 cfm h2 h1 Total heat 500 GPM T2 T1 Sensible Heat 1 085 cfm T2 T1 Total Heat Mass flow C...

Page 33: ...ven Speed Driver Speed Pitch Diameter of Driven Driver Pitch Diameter Driver Speed Driven Speed Speed of Driver Driven Pitch Diameter Driven Speed Driver Pitch Diameter Speed of Driven Driver Pitch Di...

Page 34: ...r ClimateCraft IOM 4 Inspect lighting circuit 5 Verify filter installation 6 Clean inside of unit of all construction dirt and debris 7 Adjust access doors for proper alignment as required in accordan...

Page 35: ...35 We make air handling technology Better Air Handling Unit Installation Operation and Maintenance Manual April 2021 This page intentionally left blank...

Page 36: ...com IOM SL E 041521 AHU ClimateCraft Inc All rights reserved 2021 Air Handling Unit Installation Operation and Maintenance Manual April 2021 FanMatrix and ClimateCraft are trademarks or registered tr...

Reviews: