WHAT’S IN THE BOX?
Please check the packing slip to ensure everything has been delivered.
If anything is missing, please notify your supplier within 72 hrs of receipt.
Items you will need to complete your installation:
Wall brackets to fix the vent pipe to the building
A length of 100mm DWV vent pipe (to connect to the air exhaust) (length depending on
specific installation)
You will also
require
the following materials for the Excess Fluid Absorption Trench (check
with your local Authority):
2.0m length of 100mm diameter agricultural pipe
2.0m x 0.5m synthetic or Hessian geotextile mat
0.30 cubic metre 20 mm Aggregate
50mm PVC pipe to connect the hose to the agricultural
pipe
Or
Purchase a
from Ecoflo.
The following tools will be required to complete the installation: