5-1 Commissioning ( Initial Operation )
5.0 Operation
[ Fig 5-1 ] Control Button
5-1-1 Structure of the Controller
1) Check if the voltage of the main power is within a normal range specified.
2) Cut the main power to connect the power line to the control panel.
3) Check the connection of pipes, a power supply and a grounding.
4) Fully open a stop valve on the discharge pipe of the compressed air.
5-1-2 Checklists before the Commissioning
5-1-3 Commissioning
1) Push the “START” button on the controller to check the direction of rotation. If it is operated in a
negative phase, immediately push the emergency stop button, turn the main power off, and then
convert “R” into “T” before restarting. When the compressor starts, the pressure is increased in the
airend to start the compression.
2) With the discharge valve closed on the discharge side of the air tank, check if the compressor is
automatically stopped, when the pressure reaches the set value.
3) Check if there is any abnormal vibration, noise and leakage.
4) Push the “STOP” button on the controller.