Put DSW 1.3 ON. Smart charging will be activated.
Set the DIP switches of DSW1 on the maximal available power. And leave the rest of the
DIP switches on OFF.
Example 10A
DSW 1.6 OFF
DSW 1.7 OFF
DSW 1.8 OFF
10A
13A
16A
Maximal current strength
20A
25A
32A
Settings on DSW1
1 of 3-phase
See installation manual KEBA P20/P30 for more information
Option 4.2 - Connecting ICU charging station
Install a circuit breaker or earth leakage circuit breaker for each charging
station at the maximal power available
. See p. 10.
Follow the installation instructions of the charging station. These
instructions can be found in the installation manual of the charging
station.
Place a suitable UTP (CAT5 or CAT6) cable from the charging station to Maxem and
clench RJ45 connectors on both sides.
Connect the UTP cable to the Ethernet port of the charging station and the ETH port
of Maxem.
It is possible to update the charging station firmware. This can be done via ICU
Connect, as soon as the charging station is online. ICU or Cohere can assist you with
this.
It is advisable to test the network cable with the help of a cable tester.
A
A
167
184
55.50
SECTION A-A
Client:
Rev. nr:
1:1
Units:
1/2
CES-01 - Enclosure
MH
Vol. (mm³):
mm
Sheet:
Scale:
-
Cohere
Date:
Drawn:
File reference:
Drawing name:
-
Material:
17-02-2016
Maxem 4 Assembly
A3
Stereo Design | Zamenhofstraat 150 - unit 336 | 1022AG | Amsterdam | Netherlands | T: +31 (0) 20 636 0671 | M: info@stereodesign.nl
<0,2x45° or R<0,2
Ra 0,8 um
Default length tolerances: DIN 7168
±20'
Default angle tol.:
Finish:
Default edges:
Roughness:
Tol.: ±0,1 ±0,2 ±0,3 ±0,5 ±0,8
Dim.: 0-6 7-30 31-120 121-400 401-1000
Data activity on ETH port
Maxem
ETH port ICU
UTP cable with RJ45 connectors
Take off the voltage on Keba P20/P30 (the DIP switch settings only become active after
a reset of the charging station).
16
17
A.
B.
C.
D.
E.
F.
G.