21
PART VI
STARTING THE FREEZER
Only after the machine has been thoroughly cleaned and sanitized
is the unit ready for production.
Start the machine as follows:
1) Fill the tank with mix. Total capacity is 6 qts each. never fill
the tank higher than the top of the gravity feed tube sleeve
(See the illustration on next column).
Temperature of mix should be not more than 44°F.
SUGGESTION: When initially pouring mix into the tank, it is
recommended the dispense handle be opened to allow any
residual sanitizer to be “chased” out by the mix entering the
cylinder. Place a cup under the dispense head to catch any
residual sanitizer, 2-3 oz. is sufficient to purge the sanitizer out.
571.2
L2
L3
2) Insert gravity feed tube(s) into the hole(s) at the bottom
of the mix tank.
3) Adjust the sleeve position to obtain a flow of mix in the
cylinder, according to the thickness of the mix.
Sleeve position for overrun adjusting:
Downward (greater overrun)
Upward (less overrun).
4) Push selector button 571.2 to select the “AUTOMATIC”
position.
Mix Intake
Max. Fill Level
Air Intake
Production
Maximum
Standard