17
Insert the splash guards into the top hole of the
gravity feed tube.
Lightly lubricate both orings on each tube with the
sanitary lubricant. When finished, place a feed tube
uninstalled at the bottom of each mix tank.
The machine is now completely assembled and
ready to be sanitized.
D) Assembling the Mix Injection Pump
Before assembling the mix injection pumps, locate
all of the parts that will be required.
(See Below)
First install the small oring (#1197) onto the pressure
relief plunger (#105) and lightly lubricate the oring.
NOTE: Oring #1126 is slightly smaller than the
other orings used on this assembly. Locate these
orings first and install.
Assemble the connecting tube (#207) with the
check valve (#31) and orings (#1126) and (#1117).
Lightly lubricate the check valve before installing
into the connecting tube.
Lightly lubricate both orings.
Install the two orings (#1126) into the bottom
grooves of the feeding elbows (#32) then lightly
lubricate.
Install the assembled pressure relief plunger into
the feed elbows, small end first. Next install the
assembled connecting tube into the mix feed elbow,
check valve first. The feeding elbows are now
completely assembled and can be placed into the
bottom of the mix storage tanks.
Lubricate
207
1117
1197
105
39
248
1178
38A
202
550
38
1126
32A
245
206
1126
271
1126
8
31
32