Service and inspections may only be carried out by a competent person. 
The inspection must determine that all safety devices are present and fully operational and covers the condition of the hoist, lifting gear, 
accessories and supporting constructions. 
The service intervals and inspections noted are for normal working conditions. Adverse working conditions, e. g. heat or chemical 
environments, can dictate shorter periods. 
• Yaletrac Mini electric winches are classified according to FEM/ISO in the mechanism group 1Bm/M3. This results in the theoretical 
duration of use of 400 full-load hours. 
This is equivalent to 10 years under normal operating conditions. After this period the hoist requires a general overhaul by the 
manufacturer or by a specialist. 

Attention: Maintenance work requires subsequent function testing with nominal load. 

Daily Checks 

• Visually check the pendant control switch and all cable for damage. 
• Check the proper fastening of the rope winches to the supporting structure. 
• Function check of the brakes (incl. triggering the EMERGENCY STOP button) 
• Function check of the limit switches 
• Function check of all installed safety devices 

Regular Inspections, Service And Testing 

According to the existing national/international accident prevention or safety specifications, lifting units must be checked 
• At least once per year by a competent person 
• According to the risk assessment of the operating company,  
• Before the initial start-up,  
• Before restart following a shutdown 
• After basic alterations. The concerned use conditions (e.g. operation in galvanizing facilities) can dictate shorter inspection intervals.  
Repair work may only be carried out by a specialist workshop that uses original Yale spare parts. The inspection (mainly consisting of a 
visual inspection and a function check) must determine that all safety devices are complete and fully operational and cover the condition 
of the unit, suspension, equipment and supporting structure with regard to damage, wear, corrosion or any other alterations. 
Initial operation and recurring inspections must be documented (e.g. in the CMCO works certificate of compliance). 
If required by the trade association, the results of inspections and appropriate repairs must be verified.  
If the hoist (from 1 t lifting weight) is fitted on or in a trolley, or if the hoist is used to move a lifted load in one or several directions, the 
installation is considered to be a crane and the further inspections must be carried out, in accordance with DGUV Vorschrift 54 Cranes. 
Paint damage should be touched up in order to avoid corrosion. All joints and sliding surfaces should be slightly lubricated. In case of 
heavy contamination, the unit must be cleaned. 

ATTENTION! Power supply must be disconnected while inspecting the device, unless the type of the examination excludes 
this! 

Daily checks by the regulator 

• Check the proper fastening of the Yale continuous winch to the suspension. 
• Check the working of the UP and DOWN as well as the EMERGENCY STOP buttons. 
• Check the working of the upper EMERGENCY limit switches: If the trigger is pressed manually during the upward movement of the 
unit, the load should stop immediately. 

Maintenance of the wire rope 

ATTENTION: Always wear protection gloves for handling wire ropes. 

Only original Yale wire ropes in good condition shall be used. 
The Yale continuous winches are specially designed for this wire rope. For this reason only ropes that have been explicitly approved by 
the manufacturer for these units shall be used. 
A worn wire rope must be replaced only by a wire rope of the same type, dimensions and quality. 

www.hoistandwinch.co.uk

Summary of Contents for Yale Mtrac Mini

Page 1: ...Products GmbH EN Translated Operating Instructions Also applicable for special versions Endless winch YaleMtrac Mini Columbus McKinnon Industrial Products GmbH Yale Allee 30 42329 Wuppertal Germany w...

Page 2: ...9 Theoretical service life 19 Regulations 19 Safety equipment 19 Correct operation 19 Incorrect operation 20 Assembly 22 Electrical Connection 22 Inspection before initial operation 26 Operation 27 In...

Page 3: ...Before the initial start up a check must be performed by a competent person as per the mandatory accident prevention rules applicable in the user s country as well as in accordance with the recognised...

Page 4: ...ions but also the conditions for inspection and maintenance must be complied with If defects are found or abnormal noise is to be heard stop using the hoist trolley immediately ATTENTION Disconnect th...

Page 5: ...sling rope Do not pull the rope over edges Do not tie knots in the rope or extend or shorten it by using rope clamps screws or similar Ropes must not be repaired The loose end of the rope must not be...

Page 6: ...e the rope not included in delivery scope Installation of the Yale continuous winch The Yale continuous winches are to be fastened in such a way that when viewed from any direction the loaded rope alw...

Page 7: ...pe must always be mildly lubricated Use simple multi purpose oil or grease for lubrication Molybdenum disulphide MoS2 or PTFE containing lubricants are not to be used Inserting the rope Connect the su...

Page 8: ...h suspension bolt 14 and retaining ring 2 Then install suspension bar on the main unit with suspension bolts 5 and roll pin 4 Slide support rope with the tip of the cable through the spring kit 6 and...

Page 9: ...load of the rope so that the wedge and rope settle in The wedge must be seated accurately before the system is put into operation The dead rope end must be secured so that the rope is prevented from p...

Page 10: ...ing the upward movement The load movement must be stopped immediately INSPECTION BEFORE INITIAL OPERATION According to the existing national international accident prevention or safety specifications...

Page 11: ...suitable training and be competent Operators are to be specifically nominated by the company and must be familiar with all relevant safety regulations of the country of use Application or fastening o...

Page 12: ...ple The load is then distributed to several rope falls The following requirements must be fulfilled A competent person must establish that the load capacity of the return pulley is adequate The return...

Page 13: ...that uses original Yale spare parts The inspection mainly consisting of a visual inspection and a function check must determine that all safety devices are complete and fully operational and cover the...

Page 14: ...ons and it does not require any special inspection Under more difficult conditions make sure that sufficient volume of air is provided to the motor at all times For this the unit must be regularly cle...

Page 15: ...31 2019 Columbus McKinnon Industrial Products GmbH w w w h o i s t a n d w i n c h c o u k...

Page 16: ...32 2019 Columbus McKinnon Industrial Products GmbH w w w h o i s t a n d w i n c h c o u k...

Reviews: