USER MANUAL FOR MBDA-200S
ENU STATUS : 1-0-0
Copyright - refer to title page
Page 16
3.2.2 SYSTEM INSTALLATION CHECKLIST
Working space available for installation and maintenance for each mounting arrangement. Ensure
unrestricted airflow.
Ensure earthing point is within reach of the ground wire. (2m; 6 ft. 10 in.).
Ensure a power source is within reach of the power cord and the power source has sufficient
capacity.
Where appropriate, ensure unused RF connectors are terminated.
Where appropriate, ensure unused optical fiber connectors are protected.
Do not locate the equipment near large transformers or motors that may cause electromagnetic
interference.
Reduce signal loss in feeder cable by minimizing the length and number of RF connections.
Ensure the equipment will be operated within the stated environment (refer to datasheet).
Where appropriate, confirm available of suitably terminated grade of RF.
Observe handling of all cables to prevent damage.
3.3 INSTALLATION PROCEDURES
3.3.1 GOODS INWARDS INSPECTION
mBDA was factory tested, inspected, packed, and delivered to the carrier with utmost care. Do not accept
shipment from carrier which shows damage or shortage until the carrier
’s agent endorses a statement of
the irregularity on the face of the carrier
’s receipt. Without documentary evidence, a claim cannot be
processed.
Open and check each package against the packing list. For any shortage, contact Comba Telecom
Systems. Do not remove items from packing materials until installation.
3.3.2 TOOLS
See Appendix A for a full list of tools required for installation and maintenance.