Installation and commissioning
27
6. Installation and commissioning
6.1. Requirements concerning the installation location
6.1.1. Installation location
The location must be even.
When choosing the installation location the following must be kept in mind: the flow of
the cooling air must not be restricted, coolant inlet and coolant outlet connections must
be easily accessible and all hoses must be installed without sharp bends.
6.1.2. Environmental conditions
NOTE
Risk of damage through unsuitable environmental conditions!
Damage to unit and corrosion damage may result and are not covered by
manufacturer’s liability.
The unit is only authorized for use in indoor environments.
The unit must not be stored or operated in aggressive, humid environments.
The unit must not be stored or operated outdoor.
Environmental conditions: see "Technical specifications"
6.1.3. Infrastructure
The following infrastructure is required for connecting the unit:
Parameter
Rated value
Operating voltage
230 VAC + 10% / - 15%, 50/60 Hz
6.1.4. Placing the unit
Place the unit in a way that air intake and air discharge are not obstructed. Otherwise the cooling
capacity may be restricted. The clearance with the wall of the unit is shown in the figure 5.
Figure 5: Required clearance with the wall of the unit
(1) Ventilation grids