2. Using AWG 14 (1.6 mm) solid copper wire, secure a crimp lug to one end of the
ground wire (installer provided). Secure the crimp lug to panel with two M4
screws. Torque the screws to approximately 15 pound-inches (1.7 Newton
meters).
3. Connect the other end of the ground wire to the earth ground conductor. Ensure
this connection is made using methods and hardware that meets all applicable
local and national electrical codes.
4
OPERATION
4.1
Loading Adapter Packs or Modules
For an adapter pack or module to be loaded, the designated blade must be slid out to
the “first position” and then the “second position,” providing access to press the module
or adapter pack unto the blade. Use the following procedure.
1. To slide out a blade to the first (access) position, pull out the pull arm on the right
side of the panel until the blade contacts the first detent, as shown in
Figure 11
.
Figure 11. Sliding Out Blade to First Position
PULL
ARM
26409-A