Page 6 of 20.
© 2019 CommScope, Inc.
TC-96272-IP
2
Unpacking and Inspection
1.
Inspect the exterior of the shipping container(s) for evidence of rough handling that may
have damaged the components in the container.
2.
Unpack each container while carefully checking the contents for damage.
3.
If damage is detected or if parts are missing, file a claim with the commercial carrier and
notify CommScope Support Center at
https:wwwcommscope.com//SupportCenter
4.
Save all shipping containers for use if the equipment requires shipment at a future date.
3
Overview of Installation
The main steps in installation are:
•
Mounting the cabinet on a Flex Frame or wall
•
Preparing and installing cables
•
Loading splice trays
4
Mounting the Cabinet
4.1
Mounting Options
The cabinet may be mounted on the Flex Frame or on a wall if mounting with wall mounting
brackets. Catalog numbers vary for different mounting.
•
Mounting to Flex Frame (760242402, cabinet shipped with Flex Frame)
•
Mounting to Flex Frame (760242404, cabinet alone)
•
Mounting to wall (760243212, cabinet alone, shipped with wall mounting brackets)
4.2
Tools Required
•
Phillips #2 screwdriver
•
Level (when wall mounting)
Table 3: Splice Cabinet Capacity in Flex Frame Application
Parameter
Specification
Total number of splices
5184 mass fusion, rollable ribbon splices
Number of splice trays
18 (FOST-ACC-D-TRAY-RR-288-KIT)
Panel stubs
18 rollable ribbon cable stubs (each has twenty-four 12-fiber
ribbons)
Facility cables
Common applications include nine 576-fiber cables, six 864-
fiber cables, or three 1728-fiber cables
Flex Frame panels
Eighteen EHD or CHD 2RU panels or
nine EHD or CHD 4RU panels