TECP-90-708 • Issue 5 • April 2017
Page 35
© 2017, CommScope, Inc.
8. Install the edge protector on the FOTSP in the location shown in
Figure 32
.
9. Install the hole cover in the location shown in
Figure 29 on Page 32
.
10. Re-install the front and rear troughs, as shown in
Figure 26 on Page 30
.
11. Re-install FOTSP front and rear guard boxes (reverse of steps 3 and 4, and reverse of what
is shown in
Figure 27 on Page 31
and
Figure 28 on Page 31
).
5
INSTALLING A RAISED FLOOR CABLE BRACKET
If cables will be brought into the frame from under the raised floor, a Raised Floor Standard
Cable Clamp Bracket (available from CommScope) must be installed on the rear side of the
frame in the bottom right corner.
The kit is designed for standard size cables, with an Outside Diameter (OD) of up to 0.8 in.
(2.03 mm). If large cables are to be installed, with an OD in the range from 0.8 to 1.03 in. (2.03
to 26.16 mm), a large cable kit (NG4-ACCRFCLMP3) is also required.
This procedure covers both standard and large cables, and assumes that the installer has the kit
or kits required.
Use the following procedure to install a raised floor cable clamp bracket.
1. Determine whether the cables to be installed are standard or large as defined above. Set
out the bracket plate (largest piece in the kit) and identify the hole pattern to be used for
mounting cables, referring to
Figure 33 on Page 36
. There are separate hole patterns for
large and standard cables.