7.4
Close the housing.
8
Patch application
8�1
Cable preparation, routing and
splicing at tray 2
In the patch application splicing is only possible at tray 2.
8.1.1
As supplied. Panel with adapters, pre-conn 900µ
pigtails and overlength stored.
8.1.2
Take out the 900µ pigtails.
7
Organizer installation in housing
7.1
Install the organizer in the housing by sliding the
organizer under the 2 screws.
7.2
Tighten the 3 screws.
7.3
Install blind plugs in all unused ports. Verify that
all fibers are properly routed via wire saddles (to avoid fiber
clamping).