6.6.4.10 Performing remote relay tests
Select “
Remote Test
” in the settings menu, then press the
<Set>
key.
The list with the remote relay tests appears, the first relay test is
shown.
Press the
< >
and
< >
keys in order to select the further relay tests
available and press the
<Set>
key to activate/deactivate the correspond-
ing relay for testing.
–
StandbyDelay
:
Setting the period of time in standby operation after which an automatic
cylinder draining takes place.
Factory setting:
72 hours
Setting range:
1...720 hours
–
Force Drain
:
Activating/Deactivating the forced draining which takes place after a cer-
tain time of operation. The forced draining takes place also during steam
production.
Factory setting:
Off
Options:
On
(Forced draining activated)
Off
(Forced draining deactivated)
–
Force Delay
:
Setting the time of operation after which a forced draining takes place.
Factory setting:
72 hours
Setting range:
1...720 hours
Settings
Water Manag.:Set
Remote Test :Set
Bath Test :Set
GFCI-Mode :Aus
Contrast :15
Esc
Set
Remote Test
Remote Steam:
Off
Esc
Set
Remote Service:
Off
12.00.00
Remote Error:
Off
Remote Unit On:
On
.11.2006 12.00.00