Pre-installation Preparation (cont.)
Pre-installation Alignment:
Before anchoring the cabinets to the floor, we recommend laying out the lane and testing
alignment.
Place the cabinets in their approximate end location and connect the 2 conductor cable
inside of the primary cabinet to the end in the secondary cabinet. Plug in the primary
cabinet to AC voltage to power up the lane.
Inside of the primary cabinet, there is a series of 7 total photo cell sensors. Each of these
sensors is equipped with two LED’s on the rear. One of them is green and should always
be lit. The other should be solid orange while the beam is uncrossed and off while the
beam is crossed.
If the orange LED is blinking in any case, you will need to adjust the sensor alignment,
shift the cabinets so that they are straight to each other, or shim the cabinets so that they
are level.
See the sensor alignment section of this manual
for advice on how to ensure the
transmitter’s light reaches the receiver properly.
Glass Information:
To conceal the sensor array, a sheet of tinted glass is to be installed onto the front panels.
This glass can create a dispursion effect to the sensor beams. It is suggested that the
lane’s function is tested with the glass in place to ensure alignment is sufficient for the
final installation.
Security Begins With Controlled Access