INSTALLATION
Tools Required
9/16” socket or wrench, #2 Phillips head screwdriver,
flathead screwdriver, and electrical wiring tools as needed.
1.
With housing lying on a smooth, soft surface open the
access door by rotating the front door latch 1/4 turn.
2. The door may be removed by opening approximately
120° and lifting off the hinge and by disconnecting the
green wire lanyard.
3. Using a 9/16” socket, loosen the two pipe clamp
bolts(4) enough to allow mounting arm (not included) to
slide onto leveling steps. (Figures 1 & 2.)
ote:
N
A bird guard is provided pre-cut to accommodate
1-1/2” diameter mounting arms. When using larger
diameter mounting arms, remove the punch out
section of the bird guard. (Figure 3.)
4. Lift the housing into place and position end of mounting
arm onto leveling steps so that housing is level. Care
must be taken so arm does not inadvertently strike
internal components. (Figure 4.)
5. If using a 1-1/2” pipe, remove the clamp bolts and flip
clamps so that pipe size is visible from the top. The
clamps must be reversed for the smaller pipe size
option. (Figure 2.)
6. Using a 9/16” socket, tighten the clamp bolts to 16-18
ft-lbs.
(4) Bolts 3/8”
(2) Pipe Clamps
Leveling Steps
Bird Guard
Cutout for Larger
Diameter Arm
Door Latch
Leveling Steps
Door Latch
(4) Bolts 3/8”
(2) Pipe Clamps
Bird Guard
Figure 2.
Figure 1.