HOW TO COMMISSION THIS DEHUMIDIFIER
Procedure
a) Check the electrical installation before starting the dehumidifier, switch on the mains
switch.
•
400V
– Check the voltage between the terminals L1, L2, L3
(= 400V). If Neutral is present then check one of the phases and Neutral (= 230V)
•
230V
– Check phase and Neutral (= 230V)
•
Is the ground cable connected, and of the correct specifications?
•
Is any hygrometer (if fitted) correctly connected?
b) To check the connected duct system
•
Is the recommended damper installed in the regeneration air outlet duct
•
Is the recommended damper installed in the process air outlet duct
•
Do the regeneration air outlet ducts drain away from the dehumidifier, to make sure that any
condensed water flows away?
•
If the regeneration air outlet does not drain away from the dehumidifier, check whether there
is a 6mm-diameter hole drilled in the lowest part of the duct, so that any accumulated water
can drain away.
c) Suggested damper positions/air flow settings at commissioning
Dampers/settings should be set in the following positions.
o
Damper at process air outlet: Fully open.
o
Damper at regeneration air outlet: Fully open.
NOTE
Only trained/authorised electricians are allowed to carry out any work required in the
electrical box of this Cotes dehumidifier.
When the cover of the electrical box is open, the power supply must be switched off at the
mains switch.
NOTE
You should never just turn off the power to the dehumidifier while it is running.
The correct procedure is to switch the rotary switch to neutral position,
after which the machine runs a cooling cycle before the regeneration air fan stops.