INSTALLATION MANUAL
INSTALLATION
PREPARATION
19
Foundation preparation
The Horizon cover requires a clean, flat and
level surface such as an engineered wood
deck or a concrete slab.
Each of the two jacks of the Covana cover
must be properly fastened to the tub frame. It
is the installer
’s responsibility to ensure the
Horizon cover is properly fastened in a safe
manner.
If
you
cannot
meet
these
requirements, Covana offers the ground
anchoring option for the Horizon. It is the
installer’s responsibility to ensure the Horizon
cover is properly anchored to the ground with
the proper anchoring hardware.
WARNING
The ground anchoring option should not be
used in an excessively windy area.
Just like the hot tub, the Horizon cover
requires a solid foundation. The foundation for
the Horizon cover must be able to support at
least 550 lb. (250 kg).
The foundation must be levelled with a
maximum tolerance of 1 in. (2.5 cm) over a
113 3/4 in. (2.89 m) by 56½ in. (1.44 m)
rectangle (Figure 29). Refer to
Frame
dimension
and
foot
section
for
information on minimum base size. The
annual variation in levelness for the same area
cannot exceed 1/4 in. (6 mm).
CAUTION
Damage caused by inadequate foundation
construction is not covered by the Covana
warranty. It is the
owner’s responsibility to
provide a proper foundation.
Failure to follow these guidelines may cause
permanent
damage
or
the
improper
functioning of the Covana cover. Such
damage may not be covered by the warranty.
56½ in. (1.44 m)
Figure 29
11
3
3/4
in.
(2.8
9
m
)
Summary of Contents for C-HOR
Page 1: ...Revision 13 2018 04 23...
Page 53: ...INSTALLATION MANUAL APPENDIX 53 APPENDIX...
Page 54: ...54 APPENDIX INSTALLATION MANUAL Wiring diagram North America 60 Hz 120 VAC Operator...
Page 55: ...INSTALLATION MANUAL APPENDIX 55 Wiring diagram Europe 50 Hz 220 VAC Operator...