12. Add sufficient clean fresh water to all the tanks (see
section 4 for tank details). Ensure the water level is
above both agitators in the main tank.
13. Select the spray pump’s water source to be the main
tank / SPRAY.
14. Make sure the Fan (gearbox) is in the middle /
neutral position (see page 18), and nozzles are on.
15. The pump pressure manifold will have taps for
AGITATION, BASKET (rinse) and PROBE.
Turn all of these to the OFF position. These will be
checked once the system is pressurised.
16. Ensure all spray function controls are in the OFF /
bypass position.
This will vary depending upon the controller used.
For the manual controller,
set to the BYPASS position.
For the Braglia Electric controller,
before start-up
make sure all switches are in the off position.
The master switch has 2 off positions. The fully down OFF
position (shown above) will draw power (light is on). The
bypass (dump) valve is open and there will be no pressure.
The middle OFF position will draw no power, the pressure
relief valve is active. With the PTO running, the pressure
will show on the gauge.
Note: Re this controller, always finish with the master switch
in the middle off position (to avoid a flat battery).