HT-OMCROPLINE-E
52
For the
HV2400, HV4000
or
Bravo 180S
auto rate
controllers, follow the controller instructions / operator’s
manual set them to “HOLD”. This will open the servo
“dump” valve to tank.
17. Power up the tractor (brakes on) and engage the
PTO - no need for full power at this stage, set to
approximately 350rpm.
18. At this stage the pump will be drawing from the
main tank and bypassing (dumping at) the pressure
regulator back to the tank via the return hose.
19. Activate the spray controls, to confirm the spraying
functionality. This operation will vary depending upon
the controller used. See the appropriate manuals
(for electric / auto rate controllers) and following
instructions for operation of the manual controller and
setting system pressures.
The following pictures shown he HV2400, HV4000 and
Bravo 180S controllers in “run” mode.
At this stage the Fieni fan is not operating.
While water is being pumped / sprayed through left,
right, and then both sets of nozzle manifolds check for any
leakages or blockages throughout the sprayer.
Check hoses, connections, valves, filters, boom fittings
etc. Also check nozzles are operating correctly and that
roll-overs are aligned and working correctly. Rectify
any problems.