10.2.11 Test & Commissioning
Test and commissioning is an important step to allow customer to verify the performance
achieved, and formally approve the system to enter operational status. The most important
part of test and commissioning is of course a mutually agreed test plan and commissioning
criteria.
The experienced system integrator can probably propose this test and commissioning plan early
in the project. This is particularly valid if the system integrator has done similar jobs before.
However, sometimes a T&C document too early in the way will make it very difficult to
accommodate for surprisingly low performances due to some uncontrollable environmental or
business process related factors. So really it is at the system integrator’s own discretion and
wisdom when it should best be proposed.
Testing & Verification
Commissioning Round #2
Pre-commission Training Revision
Commissioning Round #1
Further Tuning
Final Acceptance & Transfer
Intermission Period Independently Handled by Customer
Final Full Scale Installation On Site
Full Scale Tag Issuing & Correlation