8. Installation
General
This chapter is for those who are responsible for one or more of the
installations required for CTC EcoFlex to function as the property owner
wishes. Take the time required to go through the functions, controls and
settings with the property owner and answer any questions he/she may
have.
Both you and the boiler benefit from ensuring that the user fully understand
how the system works and how it should be operated.
Transport
Transport the boiler to the installation site before the packaging is removed.
Move the CTC EcoFlex in one of the following ways:
• Fork lift truck
• Lifting strap around the pallet. NB! Only to be used with packaging in
place. Handle with care.
• Lifting eye which is fitted to the expansion line socket. NB! The socket
is not at the centre of gravity. The boiler will lean to one side.
Removal of packaging
The packaging can be removed when the boiler is alongside the installation
point. Check that the product has not been damaged in transport. Report
any transport damage to the shipping agent. Also check that the below
items are included in the delivery.
Standard delivery
• Pellet boiler CTC EcoFlex
• Indoor sensor
• Primary flow sensor
• Outdoor sensor
• DHW storage tank sensor
• Drain valve
• Sweeping equipment
Boiler room
The boiler room must correspond to existing building regulations and
particularly then the firing regulations of the present country. The boiler
should be set directly on the floor. The boiler’s adjustable feet can be used
to compensate for uneven floors, up to a certain extent. Minimum distance
in front of the boiler is 1000 mm. The boiler room must be equipped with a
venthole for air supply. The cross section area of the venthole must minimum
be equal to the flue gas channel area in the chimney.
Summary of Contents for ecoflex
Page 2: ......
Page 53: ...53 CTC EcoFlex Installation 13 Electric diagram 230V 1N ...
Page 54: ...54 CTC EcoFlex Installation 14 Electric diagram 400V 3N ...
Page 56: ...56 CTC EcoFlex Installation Declaration of Conformity ...
Page 57: ......
Page 58: ......
Page 59: ......
Page 60: ...Enertech AB P O Box 309 SE 341 26 Ljungby Sweden www ctc se www ctc heating com ...