PNEG-240
Chain Feeding System
21
6. Installation
Installation Sequence
This manual outlines the recommended sequence for the installation of the Chain Feeder System.
Observing this sequence will provide the safest and easiest method of installation. Above all, connection
of the system to the electrical mains should be the final stage of installation. Failure to observe these steps
could lead to a fatal accident.
Installing the Feeder
Start by locating the exact position of the feeder in the poultry house. In some cases this may be dictated
by the position of the existing feed tanks and fill system. It is better, however, to adjust the fill system to
match the best feeder location. In new houses, always install the feeders first and install the fill system
to match.
Figure 6A
Set the feeder hopper/power unit in its proper location. From this, the trough circuits can be located in the
house. It is best to locate the hopper so the corner on the outgoing side is a minimum of 12" away from
the hopper. This will allow distance for the slack in the chain to straighten out to prevent the chain from
binding in the corner.
Ref #
Description
A
Chain Travel
B
12" Minimum (30-1/2 cm)