background image

    

Custers Hydraulica B.V. Venray NL

 

7-jan-

21

 

www.custers.nl

 

 

8

 

 

 

Figure 3 

If the mobile scaffold tower is placed against a wall, do not remove the support leg/arch, but 
turn it parallel to the wall. If the mobile scaffold tower is placed in a corner, remove the inner 
support leg and turn the outer two parallel to the wall. 
 
If the mobile scaffold tower is placed against the facade (distance between facade and 
platform not greater than 15 cm) the edge protection (hip railing, knee railing and toeboard) 
to the facade side may be left out. 
 
 

5.6.

 

 Handrail frames 

In  order  to  prevent  the  risk  of  falling  during  assembly  or  dismantling  of  the  mobile 
scaffold tower, hip railing must be present before accessing the platform. Sit on the edge 
of  the  hatch  opening  to  mount  the  railing  frames.  Only  then  can  it  be  stepped  on  the 
platform. 
 

 

Figure 4 

 
 

Summary of Contents for Amigo Mobile Scaffold Tower

Page 1: ...wer In accordance with EN1004 Maximum load 200 kg m2 Maximum platform height 4 25 metres 9505790001NL May 2020 CUSTERS HYDRAULICA B V Smakterweg 33 5804 AE VENRAY NL Telephone 31 0 478 55 30 00 P O Bo...

Page 2: ...ieerd 5 6 Handrail frames 8 6 ASSEMBLY INSTRUCTIONS 9 7 USE OF THE MOBILE SCAFFOLD TOWER 14 8 MOVING THE MOBILE SCAFFOLD TOWER 15 9 DISASSEMBLY OF THE MOBILE SCAFFOLD TOWER 16 10 MAINTENANCE OF THE MO...

Page 3: ...ult in danger for the user Read the safety instructions carefully before assembly Assembly and dismantling must be carried out by experienced and competent persons The user is responsible for the avai...

Page 4: ...utside of a material or manufacturing defect b If the cause of the failures cannot be clearly demonstrated c If all instructions given for the use of the products including the guidelines as indicated...

Page 5: ...ly instructions The amigo scaffolding can be assembled by one person The mobile scaffold tower must not be out of the plumb in excess of 1 a maximum of 1 cm inclination over a length of 1 metre check...

Page 6: ...triggers The stabilisers indicated in the table must always be installed as soon as the lower travel of the scaffolding has been assembled When assembling the upper sides of the stabilisers must be co...

Page 7: ...Custers Hydraulica B V Venray NL 7 jan 21 www custers nl 7 Figure 2 Dimensions in mm...

Page 8: ...all If the mobile scaffold tower is placed against the facade distance between facade and platform not greater than 15 cm the edge protection hip railing knee railing and toeboard to the facade side m...

Page 9: ...Amigo mobile scaffold tower can be used as a trolley 2 Remove all materials from the trolley and put them aside Leave the floor and one of the two small handrail frames Figure 6 3 Level the scaffoldi...

Page 10: ...10 Figure 7 5 Couple two four stage frames and secure them with the supplied locking pins 6 Then place these on the two four stage frames Figure 8 7 Place a floor board on the last rung of the second...

Page 11: ...aws from the inside to the outside on the uprights Figure 10 10 Again couple two four stage frames to each other and secure them with the locking clips Hang the composed frames on the arm 11 Hang two...

Page 12: ...s nl 12 Figure 11 14 Place the two coupled frames and secure them with locking clips 15 Hang the folding toeboard on the arm 16 Remove the lower floor and hang it on the same arm as the one of the toe...

Page 13: ...d seventh rung from the platform floor 19 Place the floor on the eighth rung and fold out the arms 20 Now hang all parts on the second floor 21 Climb through the hatch and sit on the edge of the hatch...

Page 14: ...be closed except when climbing or descending The maximum platform height is 4 25 metres The mobile scaffold tower may only be climbed on the inside through the frames Do not place any crates ladders...

Page 15: ...ring relocation of the stabilisers there must be an angle of 40 50 to maximise length and width The scaffolding may only be moved in the longitudinal direction by hand preferably by two people Make su...

Page 16: ...rs nl 16 9 Disassembling the mobile scaffold tower Disassembling the mobile scaffold tower takes place in reverse order Start at the top with removing the toeboards Disassemble the mobile scaffold tow...

Page 17: ...one or more dull dents with a depth of more than 3 0 mm If round tubes have one or more dents right next to a welded joint regardless of depth of the dent and shape of the dent If square rectangular t...

Page 18: ...ust be checked for proper functioning before assembly and must be free of dirt or damage Damaged parts may not be used and must be replaced or presented to the supplier for inspection assessment No to...

Page 19: ...nuary 2021 www custers nl 19 12 Parts 12 1 List of parts Figure 13 1 Swivel castor 2 Four stage frame 3 Amigo adjustable stabiliser 4 Amigo strut frame 1 20m base 5 Locking clip 6 Amigo platform 1 20m...

Page 20: ...8 12 16 Wheel with spindle 300 kg 9501 510 065 5 7 4 4 4 4 Amigo platform 1 20m with hatch 9501 790 312 9 1 1 2 2 Amigo strut frame 1 20m base 9501 790 720 4 3 4 4 6 7 Amigo toeboard set 9501 790 200...