Chapter 3
:
Replacing Components and Preventive Maintenance
66
SE500
CP
Hardware Manual
Replacing the Conveyor Clamp Cylinder
Use this procedure to replace the clamp cylinders located on the right and left sides of both the
front and back conveyor rails. This procedure can be performed with access to the left/right of
the machine in production line. This section shows the procedure performed when the machine
is not in production line.
Parts
Conveyor Clamp Cylinder
8000517 Teflon Tape
➢
To replace the conveyor clamp cylinder
1. Turn off the air supply by turning the air shut-off valve to the horizontal position.
Figure 51.
Air Shut-Off Valve
2. Disconnect the two air fitting assemblies from the side of the conveyor clamp cylinder.
Note:
Mark the connection placement for each of the assemblies
.
Figure 52.
Conveyor Clamp Cylinder
i
Note:
For Parts Replacement, contact CyberOptics for part numbers.
Air shut-off valve
SIDE VIEW
Conveyor clamp cylinder
Conveyor clamp
cylinder screw
Hall effect
switch
Hall effect
switch screw
Shoulder
screw
Summary of Contents for SE500CP
Page 1: ...SE500CP Hardware Manual ...
Page 6: ...Contents vi SE500CP Hardware Manual ...
Page 10: ...x SE500CP Hardware Manual ...
Page 170: ...Index 160 SE500CP Hardware Manual ...