Chapter 3
:
Replacing Components and Preventive Maintenance
66
SE500
CP
Hardware Manual
Replacing the Conveyor Motors
Use this procedure to replace the conveyor motors. This procedure can be performed with access
to the left/right of the machine in production line. This section shows the procedure performed
when the machine is not in production line.
Parts
DC Brushless Motor
Tools
–
Allen Key No. 2.5
➢
To replace the conveyor motors
1. Turn off all electrical power to the system. For more information, refer to the section
2. Use steps 1–9 of the procedure for removing the conveyor belt. Refer to the section “
3. Loosen the mounting screws from the motor.
Figure 54.
Conveyor Motor
4. Remove the grounding cable.
Figure 55.
Grounding cable of motor
5. Disconnect the drive motor cable.
i
Note:
For Parts Replacement, contact CyberOptics for part numbers.
Summary of Contents for SE500CP
Page 1: ...SE500CP Hardware Manual ...
Page 6: ...Contents vi SE500CP Hardware Manual ...
Page 10: ...x SE500CP Hardware Manual ...
Page 170: ...Index 160 SE500CP Hardware Manual ...