Adjusting X-Axis Parallelism
This procedure is to adjust the X-axis parallelism of the gantry stage. This procedure can be
performed with access to the left/right of the machine in production line. This section shows
the procedure performed when the machine is not in production line.
➢
To adjust the X-axis parallelism
1. Turn off all electrical power to the system. For more information, refer to the section
2. Set a target within 5 μm for the reference guideway.
3. Set a target within 5 μm for the following guideway.
Target set within 5 µm
Target within 5 µm
Tightening torque
at 90kgf.cm