Main Electrical Panel
Adjusting Y-Axis Parallelism
This procedure is to adjust the Y-axis parallelism of the gantry stage. This procedure can be
performed with access to the left/right of the machine in production line. This section shows
the procedure performed when the machine is not in production line.
➢
To adjust the Y-axis parallelism
1. Turn off all electrical power to the system. For more information, refer to the section
2. Remove the right or left side carrier.
3. Set at target within 5 μm for the reference guideway.
4. Set a target within 5 μm for the following guideway.
Carrier
Target within 5 µm
Target within 5 µm
Summary of Contents for SE500CP