Chapter 4 Operations
30
HSTP3T 15/20KE-C/KEBC-C User Manual
Chapter 4 Operations
4.1 UPS Start-up
The UPS must be started up by commissioning engineer after the completeness of
installation. The steps below must be followed
:
1. Ensure all the circuit breakers are open.
2. Close the output circuit breaker (CB) and then the input CB and the system starts
initializing. If the system has dual inputs, close both of the breakers.
3. The LCD in front of the cabinet is lit up. The system enters the home page, as shown in
Fig.3-2.
4. Notice the energy bar in the home page, and pay attention to the LED indicators. The
rectifier flashes indicating the rectifier is starting up. The LED indicators are listed below
in Table 4.1.
Table 4.1 Rectifier starting up
Indicator
Status
Indicator
Status
Rectifier
green flashing
Inverter
off
Battery
red
Load
off
Bypass
off
Status
red
5. After 30S, the rectifier indicator goes steady green, presenting the finishing of
rectification and bypass static switch closes then the inverter is starting up. The LED
indicators are listed below in Table.4.2.
Table 4.2 Inverter starting up
Indicator
Status
Indicator
Status
Rectifier
green
Inverter
green flashing
Battery
red
Load
green
Bypass
green
Status
red
6. The UPS transfers from the bypass to inverter after the inverter goes normal. The LED
indicators are listed below in Table 4.3.
Table 4.3 Supplying the load
Indicator
Status
Indicator
Status
Rectifier
green
Inverter
green
Battery
red
Load
green
Bypass
off
Status
red
7. The UPS is in Normal Mode. Close the battery circuit breakers and the UPS starts
charging the battery. The LED indicators are listed below in Table 4.4.
Table 4.4 Normal mode
Indicator
Status
Indicator
Status
Rectifier
green
Inverter
green
Battery
green
Load
green
Bypass
off
Status
green
8. The starting up done.
Note
When the system starts, the stored setting will be loaded.
Users can browse all incidents during the process of the starting up by checking the menu
Log.