CTL-618e
TOP
1. Put pads C (Figure B) under each of six points.
2. Loose set screw A (Figure B)
3. Insert a pin wrench into the hole B. raise or lower by turning (C.C.W.or .C.W)
4. Tighten set screw A (Figure B) to lock.
5. Be sure every point is touching the ground to support the machine.
Figure 1 - Lifting machine
Lifting machine, arrange rope or cable as shown in figure 1, and check to see if the correct balance has been
obtained. Then insert pads of soft cloth between the edges of the rope and machine. The net weight of this
machine is approx 1100 kgs (2420 lbs). So the rope or cable must be rated at 3000 lbs capacity.
TOP
An inspection should be made after arrival of the machine in your plant. Look for possible damage caused by
shock or vibration during transportation, also check for any missing parts, standard tools or other equipment.
In shipment, all exposed surfaces of the machine are coated with a antirust liquid. Before moving carriage
and cross-slide, lead screw, tailstock…etc, these surfaces should be thoroughly cleaned to remove all
antirust liquid use a soft brush and solvent. This is very important because it can prevent any dirt or grit which
may have accumulated on the antirust liquid from working under the sliding members and causing undue
wear.