Preparation for storage
Note:
The arrows in the illustration show all possible flow paths used during
storage preparation. The illustration shows flow from vessel
C to SIT, shown
by the green indicators.
Step
Action
1
Prepare at least 50 liters of storage buffer in both vessel
C and vessel B.
2
Open inlet
C and outlet SIT.
3
Start the pump at max 50% speed and flush the
SIT line with storage buffer.
Use about 10 to 20 liters.
4
Open outlet
SIB to flush the SIB line with storage buffer. Use about 10 to 20
liters.
Result:
Storage buffer will flush the
SIB line including the unpacking pump.
5
Open inlet
B and stop the pump when vessel B is empty.
6
Close packing station inlet and outlet valves and remove all tubing.
7
Use blind caps to seal off all TC-connections on the packing station. Now the
packing station is ready for storage according the recommended conditions
in the provided documentation.
6 Maintenance
6.2 Cleaning
6.2.1 Cleaning a Chromaflow Packing Station without a connected column
74
Chromaflow Packing Station 50, 100, 200, and 400 Operating Instructions 29046228 AD