8
DWS-1008 User’s Manual
D-Link Systems, Inc.
Installation
Installation
Equipment Rack Installation
1. Remove the four bracket screws from each side of the switch.
2. Align a bracket over the screw holes:
• For a front-mount equipment rack, align the bracket so that the bracket flange is flush
with the switch’s front panel and extends away from the switch.
• For a center-mount equipment rack, align the bracket so that the bracket flange is
located near the center screw holes.
3. Reinsert the screws to secure the brackets to the switch.
4. Repeat for the other bracket.
5. Lift the switch into position in the equipment rack.
6. Insert the bottom rack-mount screws into the bracket flanges to secure the switch to the
equipment rack, then insert the top screws.
Warning:
To prevent the switch from slipping, do not release the switch until all the
rack-mount screws are tight.
Tabletop Installation
1. On a clean work surface with no debris, carefully turn the switch upside down.
2. Wipe the four placement locations for the rubber feet to clear away any oil or dust. The
location areas are marked by X’s.
3. Attach the four rubber adhesive feet over the X’s.
4. Turn the switch right-side up, and place the switch in position on the table.
Powering On a DWS-1008 Switch
Warning:
The switch relies on the building’s installation for overcurrent protection. Ensure
that a fuse or circuit breaker no larger than 120 VAC, 15 A U.S. (240 VAC, 10 A international)
is used on the phase conductors.
1. Make sure any insertable power supply is fully seated in the switch.
2. Attach a power cord to an AC power source.
3 Plug the power cord into the power supply. The switch will begin booting as soon as you
plug in the power cord(s).
Summary of Contents for DWS-1008