Installation (continued)

14.  Feed the first rope through the large hole on the left hoisting 

bracket so that the knotted end makes contact with the 
inside of the bracket. Then, feed the rope through the left 
lifting bracket that was installed into the wall opening behind 
the T-track (See Figure 6).

15.  Repeat Step 14 for the second rope through the right and the 

third rope through the center hoisting and lifting brackets 
(See Figure 6).

 

NOTE:

 At this point, all three ropes should be fed through the 

hoisting and lifting brackets. There will be no rope placed 
through the single hoisting bracket on the bottom of the 
screen. On the rear (projector side) of the wall opening, a 
person will be needed in the following steps to guide the 
three ropes as the screen is being lifted.

 

WARNING: Do not lift the screen into place if the ropes 
have not been fed through the hoisting and lifting 
brackets.

Figure 6

Figure 7

16.  Lift the screen assembly to a vertical position on the floor 

parallel to the wall opening. On the projector side of the wall 
opening, one person will be holding all three ropes without 
slack and guiding the screen to an upright position. On the 
audience side of the wall opening, to lift there should be one 
person on the left side of the screen, one person on the right 
and one person supporting the top center of the screen 
frame at the center hoisting bracket. After this step is 
completed the screen will be standing on the floor in front of 
the wall opening (See Figure 7)

 

CAUTION: Do not allow the screen to twist or bow during 
this step. Without careful lifting, there is potential to 
crack, break or shatter the screen surface. Four people 
must be used during this step. 

Hoisting Brackets

Lifting Brackets

Summary of Contents for Polacoat Da-Plex Semi-Rigid

Page 1: ...INSTRUCTION BOOK FOR Polacoat Da Plex Semi Rigid Screen ...

Page 2: ...reen is to be installed NOTE Please read through the installation steps and note wait times The rolled screen surface needs to be acclimated to the room for 48 hours prior to installation Step 1 Once the surface is unrolled it will need to lay in its unrolled state for 4 hours Step 2 Screen Orientation Polacoat In Wall rigid rear projection screens have a polished surface and a matte coated surfac...

Page 3: ... a soft clean lint free cloth Dry Soil Marks Clean with VM P Naptha or with Da Lite Lenskleen and a soft clean lint free cloth Cleaning of Frame and Trim The exposed surfaces of the aluminum frames can be cleaned with a dilute solution of detergent and water followed by a clear water rinse Use a soft grit free cloth to preserve the anodized finish Protect screen surface during frame cleaning Do no...

Page 4: ...nrolling the screen ensure that the edge end of the surface is nearest to the floor While maintaining slight pressure on the roll cut each piece of tape wrapped around the roll at the edge end of the surface Once all tape pieces have been cut the screen surface can be unrolled This should be done gently and in at a measured pace to prevent damage to the surface There will be elastic potential ener...

Page 5: ...g the other 4 piece of trim as a guide secure the opposite end of the T track section on the end hole with a 10 screw Once both ends are attached slide the 4 trim pieces along the track to align the other positions and attach a 10 screw into the hole openings until completed See Figure 2 NOTE Sliding the trim along the T track will maintain the proper alignment when attaching the T track to the wa...

Page 6: ...ection of the screen in the opposite corner See Figure 4 8 Position the third lifting bracket 2 from the back of the T track in the center of the top section of the wall opening and mount with 1 4 X 1 lag screws See Figure 4 NOTE After completing this step there should be three lifting brackets mounted into the top section of the wall opening behind the T track Check that these brackets are secure...

Page 7: ... sections around the screen surface Attach to frame over the rubber gasket with set screws facing upwards Use a rubber mallet to gently tap the screen frame into place if needed See Figure 5 12 Starting from the center on each side tighten all set screws on all four sides of the frame using the 1 8 hex key Approximately two threads should be visible on each set screw when properly tightened 13 Pla...

Page 8: ...s being lifted WARNING Do not lift the screen into place if the ropes have not been fed through the hoisting and lifting brackets Figure 6 Figure 7 16 Lift the screen assembly to a vertical position on the floor parallel to the wall opening On the projector side of the wall opening one person will be holding all three ropes without slack and guiding the screen to an upright position On the audienc...

Page 9: ...rson should be on a ladder on the projector side helping the rope control and lifters guide the screen assembly into place until all three hoisting and lifting brackets attach to each other at the top of the wall opening See Figure 8 NOTE During this step be careful not to touch the projection coating on the audience facing side of the screen assembly along the screen edges NOTE At the end of this...

Page 10: ...hed tensioning assemblies 21 Tighten the remaining tensioning assemblies on the top section of the screen assembly until all eight four per frame section are evenly spaced and secure on the top side NOTE Use the alternating method of two to three turns on one assembly then moving on to another assembly to prevent the bolts and nuts from binding 22 At the bottom section align the T track and the fr...

Page 11: ...11 ...

Page 12: ...ite transportation expenses to and from Da Lite are payable by the purchaser and Da Lite is not responsible for damage in shipment To protect yourself against damage or loss in transit insure the product and prepay all transportation expenses TO THE MAXIMUM EXTENT PERMITTED BY APPLICABLE LAW THIS WARRANTY IS IN LIEU OF ALL OTHER WARRANTIES EXPRESS OR IMPLIED INCLUDING WARRANTIES AS TO FITNESS FOR ...

Reviews: