ENGLISH
37
PANEL MODEL
E2D 2 T E2D 3 T E2D 5 T
E2D 5 T
(230v)
E2D 8 T
E2D 15 T E2D 16 T
FUSES
16 A
25 A
32 A
25 A
50 A
63 A
63 A
PANEL MODEL E2D 15 T SD E2D 30 T SD E2D 40 T SD E2D 50 T SD E2D 60 T SD
FUSES
80 A
125 A
160 A
160 A
200 A
9.4.7
The apparatus must be correctly and safely earthed as required by the
regulations in force.
9.4.8 Depending on the type of installation, limit the maximum length of the power cable as follows:
Panel model
Max. line length
Cable Ø 1.5 mm
Max. line length
Cable Ø 2.5 mm
Max. line length
Cable Ø 4 mm
E2D 2 T
70
110
270
E2D 3 T
40
70
110
Panel model
Max. line length
Cable Ø 2.5 mm
Max. line length
Cable Ø 4 mm
Max. line length
Cable Ø 6 mm
E2D 5 T
45
70
105
E2D 5 T (230v)
15
25
40
E2D 8 T
25
45
70
Panel model
Max. line length
Cable Ø 6 mm
Max. line length
Cable Ø 10 mm
Max. line length
Cable Ø 16 mm
E2D 15 T
50
80
125
E2D 16 T
35
60
100
Panel model
Max. line length
Cable Ø 16mm
Max. line length
Cable Ø 25 mm
Max. line length
Cable Ø 35 mm
E2D 15 T SD
110
42
70
E2D 30 T SD
70
110
150
E2D 40 T SD
40
60
80
Panel model
Max. line length
Cable Ø 16mm
Max. line length
Cable Ø 25 mm
Max. line length
Cable Ø 35 mm
E2D 50 T SD
25
45
60
E2D 60 T SD
20
43
59
9.4.9
Instrumental checks to be carried out by the installer:
a)
continuity of the protection leads and of the main and supplementary equipotential circuits;
b)
insulation resistance of the electric system;
c)
test efficiency of the differential protection;
d)
test the applied voltage;
e)
test operation as indicated in points 9.5, 9.6, 9.7.
9.5
Supplying power to the control panel
After having correctly performed the steps described above, turn the selectors ref. SA1 and SA2 to position 0 and close
the panel door. Supply power to the control unit, switching on the main switch on the distribution panel. Turn on the
isolating switch ref. QS1 on the panel door. The electropumps are not fed.
.
9.6
Starting the set
1.
Ensure that the external controls are turned OFF
(control excluded).
2.
Turn the selector ref. SB1 to MAN position. The electropump P1 is fed as long as the manual impulse lasts. Repeat
the operation with selector ref. SB2. The electropump P2 is fed as long as the manual impulse lasts.
−
For systems with two floats
; following the indications in fig. page 117 the start command for pump P1 is given by
the float B, connected to the terminals 3-4, and the start command for pump P2 is given by the float C, connected to
the terminals 5-6. The stop command for both pumps is given by the float B in minimum position.
−
For systems with three floats;
following the indications in fig. page 117 the start command for pump P1 is given
by the float B, connected to the terminals 3-4, and the start command for pump P2 is given by the float C,
connected to the terminals 5-6. The stop command is given by the float A, connected to the terminals 1-2, which
acts as a minimum level float for both pumps.
Summary of Contents for E2D 2,6 M
Page 120: ...118 1 E2D E2D A B C B C A 2 3 4 5 5 1 5 2 IEC 364 5 3 EN 60204 1 6 7 IP55...
Page 122: ...120 8 2 HL1 HL2 P MAX ALARM HL3 P1 HL4 P1 KK P1 P1 HL5 P2 KK P2 P2...
Page 128: ...126 Q 7 KA1 SZ2 8 11...
Page 134: ...132 E2D 6 M HS...
Page 137: ...135 E2D 15 T SD E2D 30 T SD E2D 40 T SD E2D 50 T SD E2D 60 T SD...
Page 140: ......