Si-95
Test Operation Inverter K Series
41
Part3
Test Operation
Inverter K Series
1. Test Operation ......................................................................................42
1.1
When Power is Turned On .................................................................... 42
1.2
Outdoor Unit PC Board Ass’y ................................................................ 43
1.3
Setting Modes........................................................................................ 45
1.4
Sequential Start ..................................................................................... 51
1.5
External Control Adaptor for Outdoor Units (DTA104A61 TA104A62).. 52
1.6
Cool/Heat Mode Switching .................................................................... 56
1.7
Low Noise Operation ............................................................................. 58
1.8
Demand Control .................................................................................... 59
1.9
Wiring Check Operation ........................................................................ 60
1.10 Indoor Field Setting ............................................................................... 61
1.11 Centralized Control Group No. Setting .................................................. 63
1.12 Setting of Master Remote Controller ..................................................... 65
1.13 Remote Controller Self-Diagnosis Function .......................................... 67
1.14 Operation of the Remote Controller’s Inspection /
Test Operation Button ........................................................................... 70
1.15 Remote Controller Service Mode .......................................................... 71
SI-95.BOOK Page 41 Friday, March 31, 2000 10:59 AM