background image

 

Installation manual

9

ERQ100~140A7V1B

Inverter condensing unit

4PW51321-1

9.6.

Precautions when connecting field piping and 
regarding insulation

Be careful not to let the air handling and outdoor branch piping
come into contact with the compressor terminal cover.
If the liquid-side piping insulation might come into contact with it,
adjust the height as shown in the figure below. Also, make sure
the field piping does not touch the bolts or outer panels of the
compressor.

When the outdoor unit is installed above the air handling unit the
following can occur:
The condensated water on the stop valve can move to the air
handling unit. To avoid this, please cover the stop valve with
sealing material.

If the temperature is higher than 30°C and the humidity is higher
than RH 80%, then the thickness of the sealing materials should
be at least 20 mm in order to avoid condensation on the surface
of the sealing.

Be sure to insulate the liquid and gas-side field piping and the
refrigerant branch kit.

(The highest temperature that the gas-side piping can reach is
around 120°C, so be sure to use insulating material which is
very resistant.)

9.7.

Leak test and vacuum drying

The units were checked for leaks by the manufacturer.

See 

figure 6

 and refer to 

"Additional refrigerant charge" on page 9

 for

nomenclature of the parts in figure 6.

Confirm that the gas and liquid line stop valves are firmly closed
before pressure test or vacuuming.

Make sure that valve A is completely open.

Air tight test and vacuum drying

Air tight test: Make sure to use nitrogen gas. (For the service
port position, refer to 

"9.2. Cautions for handling stop valve" on

page 8

.

Pressurize the liquid and gas pipes to 4.0 MPa (40 bar) (do not
pressurize more than 4.0 MPa (40 bar)). If the pressure does not
drop within 24 hours, the system passes the test. If the pressure
drops, check where the nitrogen leaks from.

Vacuum drying: Use a vacuum pump which can evacuate to
–100.7 kPa (5 Torr, –755 mm Hg)

1. Evacuate the system from the liquid and gas pipes by

using a vacuum pump for more than 2 hours and bring the
system to –100.7 kPa. After keeping the system under
that condition for more than 1 hour, check if the vacuum
gauge rises or not. If it rises, the system may either
contain moisture inside or have leaks.

2.

Following should be executed if there is a possibility of
moisture remaining inside the pipe (if piping work is carried
out during the raining season or over a long period of time,
rainwater may enter the pipe during work).

After evacuating the system for 2 hours, pressurize the system to
0.05 MPa (vacuum break) with nitrogen gas and evacuate the
system again using the vacuum pump for 1 hour to –100.7 kPa
(vacuum drying). If the system cannot be evacuated to –100.7 kPa
within 2 hours, repeat the operation of vacuum break and vacuum
drying.
Then, after leaving the system in vacuum for 1 hour, confirm that
the vacuum gauge does not rise.

10. A

DDITIONAL

 

REFRIGERANT

 

CHARGE

Any exposed piping may cause condensation or burns
if touched.

2

1

3

5

5

A

4

4

6

1

Compressor

2

Terminal cover

3

Indoor and outdoor 
field piping

4

Corking, etc.

5

Insulation material 
(field supply)

6

Bolts

A

Be careful with pipe, 
bolt and outer panel 
connections

Refrigerant cannot be charged until field wiring has
been completed.

Refrigerant may only be charged after performing the
leak test and the vacuum drying (see above).

When charging a system, care shall be taken that its
maximum permissible charge is never exceeded, in
view of the danger of liquid hammer.

Charging with an unsuitable substance may cause
explosions and accidents, so always ensure that the
appropriate refrigerant (R410A) is charged.

Refrigerant containers shall be opened slowly.

Always use protective gloves and protect your eyes
when charging refrigerant.

When performing service on the unit requiring the
refrigerant system to be opened, refrigerant must be
evacuated according to local regulations.

When the power is on, please close the front
panel when leaving the unit.

Summary of Contents for ERQ100A7V1B

Page 1: ...INSTALLATION MANUAL ERQ100A7V1B ERQ125A7V1B ERQ140A7V1B Inverter condensing unit ...

Page 2: ...H 0 L2 1 2 H 1 2 H L2 H 0 L1 1 2 H 1 2 H L1 H 0 L2 1 2 H 1 2 H L2 H L2 H L2 H L2 H L2 H L2 H L2 H 150 500 500 500 500 750 100 100 100 100 200 300 200 100 250 250 500 1000 1000 1000 500 500 500 500 1000 1000 1000 1000 500 500 1000 500 1000 1000 300 300 300 250 300 300 500 200 1000 1000 1000 1000 1000 1250 1500 1500 1000 1000 100 5 4 4 3 2 1 7 8 9 10 A D C B 5 6 11 7 6 1 2 3 4 5 6 7 9 8 12 13 10 11 ...

Page 3: ... gitt i henhold til bestemmelsene i 13 noudattaen määräyksiä 14 za dodržení ustanovení předpisu 15 prema odredbama 16 követi a z 17 zgodnie z postanowieniami Dyrektyw 18 în urma prevederilor 19 ob upoštevanju določb 20 vastavalt nõuetele 21 следвайки клаузите на 22 laikantis nuostatų pateikiamų 23 ievērojot prasības kas noteiktas 24 održiavajúc ustanovenia 25 bunun koşullarına uygun olarak 01 Note...

Page 4: ... here are divided into the following two types Both cover very important topics so be sure to follow them carefully Warning Ask your dealer or qualified personnel to carry out installation work Do not install the machine by yourself Improper installation may result in water leakage electric shocks or fire Perform installation work in accordance with this installation manual Improper installation m...

Page 5: ...e air handling and outdoor units power wire and connecting wire at least 1 meter away from televisions or radios to prevent image interference or noise Depending on the radio waves a distance of 1 meter may not be sufficient to eliminate the noise Do not rinse the outdoor unit This may cause electric shocks or fire Do not install the air conditioner in places such as the following Where there is m...

Page 6: ...ect an installation site where the following conditions are satisfied and that meets with your customer s approval Places which are well ventilated Places where the unit does not bother next door neighbours Safe places which can withstand the unit s weight and vibration and where the unit can be installed level Places where there is no possibility of flammable gas or product leak Places where serv...

Page 7: ...he drain water dripping 10 The equipment is not intended for use in a potentially explosive atmosphere 5 PRECAUTIONS ON INSTALLATION Check the strength and level of the installation ground so that the unit will not cause any operating vibration or noise after installation In accordance with the foundation drawing in the figure fix the unit securely by means of the foundation bolts Prepare four set...

Page 8: ...plied vinyl hose internal diameter of 25 mm to the drain socket A If the hose is too long and hangs down fix it carefully to prevent kinks 6 INSTALLATION SERVICING SPACE The connection piping outlet direction in the installation shown in figure 4 is frontward or downward The unit of numeric values is mm When routing the piping backward secure space of 250 mm on the right side of the unit A In case...

Page 9: ...ly into the system while the pump is not working Use a vacuum pump which can evacuate to 100 7 kPa 5 Torr 755 mm Hg In order to prevent dirt liquid or dust from entering the piping cure the piping with a pinch or taping Great caution is needed when passing copper tubes through walls For handling of stop valves refer to 9 3 How to use the stop valve on page 8 Only use the flare nuts included with t...

Page 10: ... install the connecting pipe to the unit in a downward direction make a knockout hole by penetrating the center area around the knockout hole using a Ø6 mm drill See figure 5 Cutting out the two slits makes it possible to install as shown in figure 5 Use a metal saw to cut out the slits After knocking out the knock out it is recommended to apply repair paint to the edge and the surrounding end sur...

Page 11: ... flare nut may cause refrigerant leak 9 3 How to use the stop valve Use hexagonal wrenches 4 mm and 6 mm Opening the valve 1 Place the hex wrench on the valve bar and turn counter clockwise 2 Stop when the valve bar no longer turns It is now open Closing the valve 1 Place the hex wrench on the valve bar and turn clockwise 2 Stop when the valve bar no longer turns It is now closed 9 4 Cautions for ...

Page 12: ...se a vacuum pump which can evacuate to 100 7 kPa 5 Torr 755 mm Hg 1 Evacuate the system from the liquid and gas pipes by using a vacuum pump for more than 2 hours and bring the system to 100 7 kPa After keeping the system under that condition for more than 1 hour check if the vacuum gauge rises or not If it rises the system may either contain moisture inside or have leaks 2 Following should be exe...

Page 13: ...ated greenhouse gases covered by the Kyoto Protocol Do not vent gases into the atmosphere Refrigerant type R410A GWP 1 value 1975 1 GWP global warming potential Please fill in with indelible ink the factory refrigerant charge of the product the additional refrigerant amount charged in the field and the total refrigerant charge on the fluorinated greenhouse gases label supplied with the product The...

Page 14: ...initial start up Setting the mode on page 16 set the required function A additional refrigerant charging operation to ON Then operation starts The blinking H2P led indicates test operation and the remote controller indicates test operation and external control 6 When the specified amount of refrigerant is charged push the button Then operation stops The operation automatically stops within 30 minu...

Page 15: ...ircuits must be interrupted Use only copper wires Do not turn on the main switch until all the wiring is completed Make sure that the main switch has a contact separation of at least 3 mm in all poles Never squeeze bundled cables into a unit Secure the electrical wiring with clamping material as shown in figure 9 so that it does not come in contact with the piping particularly on the high pressure...

Page 16: ...oper distance between power cable and control wiring 4 Clamp field supply 5 Stop valve mounting plate 6 Power cable 7 Ground cable yellow green 8 Fix the control wiring with the clamp 9 Control terminal block X2M 1 Knockout hole 2 Burr 3 Packing materials 2 3 1 Use a power wire pipe for the power wiring Outside the unit make sure the low voltage electric wiring i e for the remote control between u...

Page 17: ...rminals for connections to the power terminal block When none are available follow the instructions below Do not connect wiring of different thicknesses to the power terminal block Slack in the power wiring may cause abnormal heat When connecting wiring which is the same thickness do as shown in the figure below For wiring use the designated power wire and connect firmly then secure to prevent out...

Page 18: ...ording to the instructions described in this manual according to the wiring diagrams and according to local and national regulations 4 Pipe sizes and pipe insulation Make sure that correct pipe sizes are installed and that the insulation work is properly executed 5 Additional refrigerant charge The amount of refrigerant to be added to the unit should be written on the included Added Refrigerant pl...

Page 19: ... 1 Led H1P H8P 2 Push button switches BS1 BS5 3 DIP switches 2 DS1 1 DS1 2 x OFF w ON c blinking For changing the set mode For field setting For field setting For test operation For resetting the address when the wiring is changed or when an additional air handling unit is installed NOTE If you get confused in the middle of the setting process push the button Then it returns to setting mode 1 H1P ...

Page 20: ...the sound of a magnetic solenoid valve may rise during this operation The following items are automatically checked Check for incorrect wiring Check if stop valves are open Check of refrigerant charge Automatic judgement of piping length 4 After the test operation maximum 30 minutes the unit automatically stops Check the operation results by the outdoor unit led indication H1P H2P H3P H4P H5P H6P ...

Page 21: ...e H1P led is on and the remote controller indicates test operation and external control and the operation will be prohibited 2 Recover the refrigerant using a refrigerant reclaimer For details see the operation manual delivered with the refrigerant reclaimer 3 Press the button and reset the setting mode 2 Installation error Malfunction code Remedial action The stop valve of an outdoor unit is left...

Page 22: ...steps 1 to 4 below and take whatever action is necessary to comply 1 Calculate the amount of refrigerant kg charged to each system separately 2 Calculate the smallest room volume m3 In a case such as the following calculate the volume of A B as a single room or as the smallest room 3 Calculating the refrigerant density using the results of the calculations in steps 1 and 2 above If the result of t...

Page 23: ...1 2 3 4 D E E E E E 9 A B C 2 2 3 2 4 7 2 9 3 2 3 5 6 1 4 8 3 2 3 16 V 1 2 3 4 230 V 6 5 TO IN D UNIT F1 F2 TO OUT D UNIT F1 F2 DS1 1 2 F1 F2 OUT IN ON OFF A2P X2M A1P A2P A4P X2M F1 F1 F2 F2 TO IN D UNIT C H SELECTOR X2M A C B A4P TO OUT D UNIT 4 A B C 1 3 2 5 F1 F2 1 2 3 4 5 8 11 12 9 10 13 14 ...

Page 24: ...4PW51321 1 Copyright Daikin ...

Reviews: