Fix the cable with cable ties to the cable tie mountings.
9.3.4 To connect the electricity meters
Wires: 2 (per meter)×0.75 mm²
Electricity meters: 12 V DC pulse detection (voltage supplied by PCB)
[9.A]
Energy metering
INFORMATION
In case of an electricity meter with transistor output, check the polarity. The positive
polarity MUST be connected to X5M/6 and X5M/4; the negative polarity to X5M/5
and X5M/3.
1
Open the following (see
"7.2.6 To open the indoor unit"
1
Top panel
1
2
3
2
User interface panel
3
Upper switch box cover
2
Connect the electricity meters cable to the appropriate terminals as shown in
the illustration below.
A
6
5
4
3
S3S S2S
Summary of Contents for ETVZ16E6V7
Page 281: ......
Page 282: ......
Page 283: ......
Page 284: ...4P644739 1A 2022 03 Copyright 2021 Daikin Verantwortung f r Energie und Umwelt...