8
|
Piping installation
Installer reference guide
83
EPRA14~18D + ET23E
Daikin Altherma 3 H HT F
4P644739-1A – 2022.03
NOTICE
If you install this unit as a single-zone application, then:
Setup.
Install a bypass between the space heating water inlet and outlet of the
additional zone (=direct zone). Do NOT interrupt the water flow by closing the shut-
off valves.
a
a
Bypass
Configuration.
Set field setting [7-02]=0 (
Number of zones
=
Single zone
).
NOTICE
Install air purge valves at all local high points.
NOTICE
A pressure relief valve (field supply) with an opening pressure of maximum 10 bar
(=1 MPa) must be installed on the domestic cold water inlet connection in
accordance with the applicable legislation.
NOTICE
▪
A drain device and pressure relief device must be installed on the cold water inlet
connection of the domestic hot water cylinder.
▪
To avoid back siphonage, it is recommended to install a non-return valve on the
water inlet of the domestic hot water tank in accordance with the applicable
legislation.
▪
It is recommended to install a pressure reducing valve on the cold water inlet in
accordance with the applicable legislation.
▪
An expansion vessel should be installed on the cold water inlet in accordance
with the applicable legislation.
▪
It is recommended to install the pressure relief valve on a higher position than
the top of the domestic hot water tank. Heating of the domestic hot water tank
causes water to expand and without pressure relief valve the water pressure
inside the tank can rise above the tank design pressure. Also the field installation
(piping, tapping points, etc.) connected to the tank is subjected to this high
pressure. To prevent this, a pressure relief valve needs to be installed. The
overpressure prevention depends on the correct operation of the field installed
pressure relief valve. If this is NOT working correctly, overpressure will deform
the tank and water leakage may occur. To confirm good operation, regular
maintenance is required.
8.2.4 To connect the recirculation piping
Prerequisite:
Only required if you need recirculation in your system.
1
Remove the top panel from the unit, see
60].
2
Cut out the rubber grommet on top of the unit, and remove the stop. The
recirculation connector is placed below the hole.
3
Route the recirculation piping through the grommet and connect it to the
recirculation connector.
Summary of Contents for ETVZ16E6V7
Page 281: ......
Page 282: ......
Page 283: ......
Page 284: ...4P644739 1A 2022 03 Copyright 2021 Daikin Verantwortung f r Energie und Umwelt...