The Controller for the EUWA/Y15-30HC(Z) Chillers
Part 2 – Functional Description
2–27
3
2
4
5
1
3.3
Start/Stop, Cool/Heat and Temperature Setting
At power on
■
The initialization takes 10 seconds.
■
The controller automatically enters the read-out menu, displaying the first read-out screen.
Remote start/stop
The procedure to start or stop the unit depends on the setting of the remote start/stop, see page 2-33.
The remote start/stop is field supply.
How to start or stop
To start or stop the unit, proceed as follows:
*: The local start/stop button
f
must be enabled (blinking) before the remote start/stop is active. If the
remote start/stop is not enabled, then the LED
f
is off.
How to cool or heat
To change from cooling to heating (or vice versa), press
d
.
■
If cooling operation is selected, the
d
LED lights up.
■
If heating operation is selected, the
d
LED blinks.
Remote cool/heat
To activate remote cool/heat, refer to page 2-33 (remote cool/heat switch is field supply).
The
d
LED does not light up when the remote cool/heat is activated.
Temperature
setting
To adjust the inlet water temperature, use the setpoints menu (
z
key), refer to page 2-32.
Remote start/stop
Start or stop
Action
Result:
f
LED …
no
start
press
f
lights up
stop
press
f
goes off
yes
initial
press
f
*
blinks
start
pull switch remote start
lights up
stop
pull switch remote stop
blinks
Summary of Contents for EUWA/Y5-30HB/C(Z)
Page 2: ......
Page 8: ...Introduction ESIE98 06A vi 3 1 4 5...
Page 10: ...ESIE98 06A 1 2 Part 1 System Outline 3 1 1 4 5...
Page 28: ...General Outline ESIE98 06A 1 20 Part 1 System Outline 3 1 1 4 5...
Page 36: ...Piping Layout ESIE98 06A 1 28 Part 1 System Outline 3 1 1 4 5...
Page 52: ...ESIE98 06A Wiring Layout Part 1 System Outline 1 44...
Page 58: ...ESIE98 06A 2 2 Part 2 Functional Description 3 1 2 4 5...
Page 100: ...ESIE98 06A 3 2 Part 3 Troubleshooting 3 1 3 4 5...
Page 134: ...Troubleshooting ESIE98 06A 3 36 Part 3 Troubleshooting 3 1 3 4 5...
Page 136: ...ESIE98 06A 4 2 Part 4 Commissioning and Test Run 3 1 4 5...
Page 142: ...Pre Test Run Checks ESIE98 06A 4 8 Part 4 Commissioning and Test Run 3 1 4 5...