General Outline
ESIE11-02
1–6
3
11
4
5
(1)
: The table below contains the minimum water volume settings.
(2)
: The sound power level is an absolute value that does not depend on the surroundings or the
distance. It cannot be measured in the field (ISO 9614).
No. of circuits
1
Pump
No. x type
__
1 x Horizontal multi-stage end-suction
__
1 x Horizontal multi-stage end-suction
Model
__
CM3-3
CM3-3
Nominal static
height pump
__
239 kPa
198 kPa
Nominal static
height unit
__
209 kPa
128 kPa
Hydraulic components
Buffer tank
__
55 l
__
55 l
Unit water volume
2 l
3 l
59 l
3 l
3 l
59 l
Expansion vessel
__
12 l
__
12 l
Pre-pressure
expansion vessel
1.5 bar
1.5 bar
Safety valve
__
3 bar
__
3 bar
Dimensions
(h x w x d)
1230 x 1290 x 734 mm
1230 x 1290 x 734 mm
Weight
Machine weight
150 kg
168 kg
180 kg
215 kg
229 kg
241 kg
Operation weight
152 kg
171 kg
239 kg
218 kg
232 kg
300 kg
Casing
Colour
Ivory white / Munsell code 5Y7.5/1 / ± RAL 7044
Material
Polyester coated galvanised steel plate
Sound power
level
(2)
67 dBA
76 dBA
Safety devices
■
Low-pressure switch
■
High-pressure switch
■
Pump motor overcurrent
■
Discharge temperature control
■
Outlet water temperature protection
■
Compressor motor overcurrent relay
■
Fan thermal protector
■
Anti-recycling and guard timer
■
Digital display controller with electronic temperature control
■
Reverse phase protector
■
Flow switch.
Model
EUWAN5KBZW1 EUWAP5KBZW1 EUWAB5KBZW1 EUWAN8KBZW1 EUWAP8KBZW1 EUWAB8KBZW1
Setting
EUWA*5-8KBZW1
The minimum water volume for standard thermostat difference setting
3 K
For reduced setting multiply this water volume by
3/new setting
Minimum allowable setting
0.1 K
Summary of Contents for EUWY 24KBZW1 Series
Page 2: ......
Page 8: ...ESIE11 02 vi Table of Contents 3 1 4 5...
Page 10: ...Introduction ESIE11 02 viii 3 1 4 5...
Page 12: ...ESIE11 02 1 2 Part 1 System Outline 3 1 1 5...
Page 86: ...Wiring Layout ESIE11 02 1 76 Part 1 System Outline...
Page 88: ...ESIE11 02 2 2 Part 2 Functional Description 3 1 2 5...
Page 128: ...The Digital Controller ESIE11 02 2 42 Part 2 Functional Description 3 1 2 4 5...
Page 130: ...ESIE11 02 3 2 Part 3 Troubleshooting 3 1 3 5...
Page 168: ...ESIE11 02 4 2 Part 4 Commissioning and Test Run 3 1 4 5...
Page 198: ...Test Run and Operation Data ESIE11 02 4 32 Part 4 Commissioning and Test Run 3 1 4 5...
Page 200: ...ESIE11 02 5 2 Part 5 Maintenance 3 1 5...
Page 210: ...ESIE11 02 4 Index 3 1 4 5...