Action

1

Connect the user interface cable to the outdoor unit.

X5M

A5P

A5P

1 2

a

b

a

 Main user interface

(a)

b

 Optional user interface

2

Insert a screwdriver into the slots underneath the user
interface and carefully separate the faceplate from the
wallplate.

The PCB is mounted in the faceplate of the user interface.
Be careful NOT to damage it.

3

Fix the wallplate of the user interface to the wall.

4

Connect as shown in 4A, 4B, 4C or 4D.

5

Reinstall the faceplate onto the wallplate.

Be careful NOT to pinch the wiring when attaching the
frontplate to the unit.

(a)

The main user interface is required for operation. It is
delivered with the unit as accessory.

4A From the rear

b

a

PCB

4B From the left

a

PCB

b

4C From the top

a

b

PCB

b

4D From the top centre

a

PCB

b

b

a

Notch this part for the wiring to pass through with nippers
etc.

b

Secure the wiring to the front part of the casing using the
wiring retainer and clamp.

4.4.4

To connect the shut-off valve

1

Connect the valve control cable to the appropriate terminals as
shown in the illustration below.

NOTICE

Only connect NO (normal open) valves.

NO

X5M

X3M

M2S

2

1

INFORMATION

By  default,  the  shut‑off  valve  is  to  be  connected  to  the
outdoor  unit.  However,  if  control  box  EKCB07CAV3  is
present  in  the  system,  you  can  also  connect  it  to  the
control  box.  To  do  this,  connect  outdoor  unit  terminals
X3M/1+2  to  control  box  terminals  X8M/6+7,  and  then
connect  the  shut‑off  valve  to  control  box  terminals
X8M/6+7.

X2M

X8M

6 7

X5M

X3M

M2S

1

2

5

Configuration

5.1

Overview: Configuration

This  chapter  describes  what  you  have  to  do  and  know  to  configure
the system after it is installed.

NOTICE

The  explanation  about  the  configuration  in  this  chapter
gives  you  ONLY  basic  explanations.  For  more  detailed
explanation  and  background  information,  see  the  installer
reference guide.

Summary of Contents for EWAQ006BAVP

Page 1: ...Packaged air cooled water chillers and packaged air to water heat pumps English Installation manual Packaged air cooled water chillers and packaged air to water heat pumps EWAQ006BAVP EWAQ008BAVP EWYQ...

Page 2: ...C 100 250 100 A B C E 150 250 150 1000 500 500 D 500 500 D E 1000 500 B D 250 500 B D E 250 250 400 400 400 400 400 1000 150 150 150 150 150 150 150 1000 1000 1000 500 HD HU HD HU HB HU HD HU HB HU a...

Page 3: ...valt meie juhenditele atitinka emiau nurodytus standartus ir arba kitus norminius dokumentus su s lyga kad yra naudojami pagal m s nurodymus tad ja lietoti atbilsto i ra ot ja nor d jumiem atbilst sek...

Page 4: ...ut 18 7 Hand over to the user 18 7 1 About locking and unlocking 19 To activate or deactivate a function lock 19 To activate or deactivate button lock 19 8 Technical data 20 8 1 Piping diagram Outdoor...

Page 5: ...ivered with the outdoor unit 3 Preparation 3 1 Preparing installation site 3 1 1 Installation site requirements of the outdoor unit Mind the spacing guidelines See figure 1 on the inside of the front...

Page 6: ...electrical connections for external and internal actuators Item Description Wires Maximum running current Outdoor unit power supply 1 Power supply for outdoor unit 2 GND a 2 Normal kWh rate power supp...

Page 7: ...properly When the unit is in cooling mode condensate may also form in the hydro part When providing drainage therefore make sure to cover the entire unit NOTICE If the unit is installed in a cold cli...

Page 8: ...peratures are expected add glycol to the water circuit The required concentration depends on the lowest expected outdoor temperature and on whether you want to protect the system from bursting or from...

Page 9: ...me of the system For more information refer to the chapter To check the water volume and flow rate in the installer reference guide 4 3 3 To fill the water circuit 1 Connect the water supply hose to t...

Page 10: ...that the cable does NOT come in contact with sharp edges 5 Install the switch box cover INFORMATION When installing field supply or option cables foresee sufficient cable length This will make it poss...

Page 11: ...b 1 4D From the top centre a PCB b b 1 a Notch this part for the wiring to pass through with nippers etc b Secure the wiring to the front part of the casing using the wiring retainer and clamp 4 4 4 T...

Page 12: ...more than 4 seconds Result is displayed on the home pages 4 If you do NOT press any button for more than 1 hour or press again for more than 4 seconds the installer permission level switches back to E...

Page 13: ...Description A 2 2 E 1 E 03 Backup heater steps 0 default 1 2 Code Description A 2 2 E 2 5 0D BUH type 1 1P 1 1 2 6 kW 1 230 V default 4 3PN 1 2 6 kW 3N 400 V 9W 5 3PN 1 1 2 9 kW 3N 400 V 9W The syste...

Page 14: ...d Absolute 1 Weather dep Weather dependent 2 Fixed scheduled Absolute scheduled only for leaving water temperature control 3 WD scheduled Weather dependent scheduled only for leaving water temperature...

Page 15: ...eaving water setpoint By setting the weather dependent curve to a higher position it cannot drop below the minimum setpoint Refer to the illustration below a 8 06 8 06 b Ta Tt a Weather dependent curv...

Page 16: ...pe Indoor software type Unit control method Pump operation mode Power saving possible User interface location Options External sensor Control box Option box Leaving water Main Delta T source Room ther...

Page 17: ...pressure relief valve purges water when opened The minimum water volume is guaranteed in all conditions See To check the water volume in 3 2 Preparing water piping on page 5 If glycol was added to th...

Page 18: ...ettings Commissioning Actuator test run 4 Select an actuator and press Example Pump 5 Select OK and press Result The actuator test run starts It automatically stops when finished To stop it manually p...

Page 19: ...er to be able to change setpoint temperatures the simplified user interface or an external room thermostat is then required You can use the following locking modes Function lock Locks a specific funct...

Page 20: ...heat exchanger 9 Safety valve 10 Water filter 11 Expansion vessel 12 R1T Outlet water heat exchanger thermistor 13 R3T Refrigerant liquid side thermistor 14 R4T Inlet water thermistor 15 Gas stop val...

Page 21: ...1P Signal transmission circuit V1D V3D A1P Diode V1R A1P IGBT power module V2R A1P Diode module V1T V2T A1P Insulated gate bipolar transistor IGBT X1M Terminal strip Y1E Electronic expansion valve Y1S...

Page 22: ...power circuit A4P Extension PCB control optional A5P User interface PCB A7P Receiver PCB wireless On OFF thermostat K1A Relay for heating K2A Relay for cooling M2S Shut OFF valve M4S Valve kit English...

Page 23: ...eter inputs 5 V DC pulse detection voltage supplied by PCB Electric pulse meter inputs 5 V DC pulse detection voltage supplied by PCB 2 Legend 2 Legend A4P Extension PCB control optional R6T External...

Page 24: ...for KRUCB A5P P1 P2 user interface A5P P1 P2 user interface Power supply 3 core control box power supply 230 V earth signal signal signal 2 or 3 core 2 core 2 core F1B L1 L2 L3 N earth or L N earth b...

Page 25: ......

Page 26: ......

Page 27: ......

Page 28: ...4P478610 1 2017 02 Copyright 2017 Daikin...

Reviews: