7 Installation
Installation manual
12
EZESHP20 EZLSHP20AUAW1B
Exigo E1500 Trailer Refrigeration Unit
4P726857-1 – 2023.03
DANGER
Always use a safety harness when working at height.
INFORMATION
Always lift the unit from above. Use an overhead crane or
the forks of a forklift, see
23] for the
weight of the unit.
1
Standing on a ladder or work-stand, hook the slings (a) onto the
fixing points (b).
a
b
a
b
a
Sling
b
Fixing point A1
2
Remove the nuts (d), washers (e) and bolts (f).
3
Remove the special transport pallet (c) from the unit.
c
d
f
c e
f d
e
f
e
e
e d f
c
c
Special transport pallet
d
Nut
e
Washer
f
Bolt
NOTICE
Do not lift the unit before all the screws are removed.
Check that no small parts (e.g. nuts, washers, screws, …)
are left inside the unit.
7
Installation
7.1
Overview: Installation
This chapter describes what you have to do and know on-site to
install the system.
Typical workflow
Installation typically consists of the following stages:
1
Installing the unit on the cold room
2
Installing the door micro switch and cold room light
3
Installing the eventual option(s)
4
Installing the fuel pump
5
Connecting the fuel lines
INFORMATION
This manual only describes installation instructions specific
to this unit. For carrying out mechanical work on the cold
room and trailer, the instructions of the cold room/trailer
manufacturer must always be followed.
INFORMATION
In some cases the installation of a splitter/duct on the
coldroom side can increase efficiency. For carrying out
mechanical work on the cold room and trailer, the
instructions of the cold room/trailer manufacturer must
always be followed.
7.2
Mounting the unit
7.2.1
Precautions when mounting the unit
WARNING
Do not remove earth connections while installing the unit.
Missing earth continuity may lead into electrocution.
INFORMATION
Also read the precautions and requirements in the
following chapters:
▪ General safety precautions
▪ Preparation
7.2.2
To position the unit
INFORMATION
Always lift the unit from above. Use an overhead crane or
the forks of a forklift, see
23] for the
weight of the unit.
1
Position the unit (a) in front of the cold room (b) by hanging it
from a lifting device (e.g. fork lift or overhead crane).