3.1 Pre-Trip Inspection
Perform a pre-trip inspection of each component and take remedial actions if necessary so that the unit will
operate normally. Pre trip inspection includes items are listed below.
(1) Appearance inspection of unit
①
Physical damage
②
Casing insulation through penetration
③
Drain hose (dust and clogging)
④
Power cable and plug damage
⑤
Condition of refrigerant piping cramp
⑥
Condition of each sensor installation
⑦
Loose mounting sections
・
Bolts and nuts ----- Casing frame, compressor, fan motor, control box, inverter box
・
Cable glands ----- Control box
⑧
Conditions of control box cover packing (water-proof)
⑨
Magnetic contactor contact point
⑩
Condition of Inverter box cover packing (water-proof)
(2) Inspection before unit operation
①
Refrigerant leakage inspection
②
Power voltage inspection (Automatic PTI range)
(3) Operation inspection of safety
device and control equipment
HPS
……
Check for proper activation of switch when high pressure
①
Safety device
is raised by stopping the condenser fan motor.
②
Control equipment
Solenoid valve
……
Inspection of operation (open and close) and leakage
EFM
……
Speed switchover and rotating direction
EEV,
EMV,
DMV
……
Inspection of operation (open and close) and leakage
(4) Operation in each mode
①
Pull-down
→
0
℃
Pull-down time, voltage and current
②
Chilled control 0
℃
Electronic temperature recorder calibration Return, supply air temperature differential, voltage and current
③
Defrosting
Defrosting time
④
Pull-down
→
-18
℃
Pull-down time, evaporator fan motor speed switchover
⑤
Frozen control -18
℃
Electronic temperature recorder calibration (Temperature difference and rotating direction)
voltage and current
⑥
Dehumidification operation and humidity sensor inspection
Remaining frost inspection
(5) PTI report preparation
●
Consumables
①
Wake-up battery: 2 years
②
Humidity sensor: Inspect every year. Replace when appropriate.
③
Refrigerant: Inspect at PTI. Repair as needed. (malfunction caused by moisture entering etc.)
④
Power plug: Inspect during PTI. Repair as needed.
⑤
Power cable: Inspect during PTI. Repair as needed.
03章̲LX10F11B3̲TR16-02̲En.indd 3-2
03章̲LX10F11B3̲TR16-02̲En.indd 3-2
2015/12/21 15:43:10
2015/12/21 15:43:10
https://daikin-p.ru
Summary of Contents for LX10F11B3
Page 7: ...https daikin p ru ...
Page 83: ...https daikin p ru ...
Page 93: ...https daikin p ru ...
Page 121: ...https daikin p ru ...
Page 129: ...https daikin p ru ...
Page 138: ...6 9 6 6 Sequence AIR WATER COOLED AIR WATER COOLED https daikin p ru ...
Page 139: ...6 10 Stereoscopic wiring diagram AIR WATER COOLED https daikin p ru ...