53
IOM 1297
WWW.DAIKINAPPLIED.COM
APPENDIx
Appendix
Pre-Start Checklist
Pre-Start Checklist – Magnetic Bearing Chillers
Must be completed, signed and returned to Daikin Applied service dept. at least 2 weeks prior to requested start date.
Job Name
Installation Location
Customer Order Number
Model Number(s)
G.O. Number(s)
Chilled Water
Yes
No
N/A
Initials
Piping Complete
Water System – flushed, filled, vented; Water treatment in place
Pumps installed and operational (rotation checked, strainers installed and cleaned)
Controls operational (3-way valves, face/bypass dampers, bypass valves, etc.)
Water system operated and tested; flow meets unit design requirement
Flow switch installed, wired, and calibrated
Condenser Water
Yes
No
N/A
Initials
Cooling tower flushed, filled, vented; Water treatment in place
Pumps installed and operational (rotation checked, strainers installed and cleaned)
Controls (3-way valves, bypass valves, etc.) operable per IM/IOM
Water system operated and flow balance to meet unit design requirement
Flow switch installed, wired, and calibrated
Electrical
Yes
No
N/A
Initials
All interlock wiring complete and compliant with Daikin Applied specifications
Pump starter and interlocks wired
Cooling tower fans and controls wired
Wiring complies with National Electrical Code and local codes
(See Note 4)
Condenser pump starting relay (CP1,2) installed and wired
(See Note 3)
Miscellaneous
Yes
No
N/A
Initials
Relief valve piping complete (per local codes)
Thermometers, wells, gauges, control, etc., installed
Minimum system load of 80% capacity available for testing/adjusting controls
SiteLine
TM
cloud-connected controls included and needs to be commissioned
Document Attached:
Technical Breakdown from Daikin Tools
Document Attached:
Final Order Acknowledgement
Notes: The most common problems delaying start-up and affecting unit reliability are:
1.
Field installed compressor motor power supply leads too small. Questions: Contact the local Daikin Applied sales representative. State size, number and type of
conductors and conduits installed:
a.
From Power supply to starter
b.
From starter to chiller unit (remote mounted)
2.
A 115-volt field-supplied relay (CP1,2) must be used to start/stop condenser water pump on most applications. Cold condenser water must not flow through
condenser during compressor off cycle. Provisions have been made in control center for connecting CP relay, but must not have a rating in excess of 100 VA.
3.
Refer to NEC Article 430-22 (a)
Contractor Representative
Daikin Applied Sales Representative
Signed:
Signed:
Name:
Name:
Company:
Company:
Date:
Date:
Phone/Email:
Phone/Email:
©2022 Daikin Applied
Form SF-220
01
06 SEPT 2022