Pre-Start Checklist – Centrifugal Chillers
Must be completed, signed and returned to Daikin Applied service dept. at least 2 weeks prior to requested start date.
Job Name
Installation Location
Customer Order Number
Model Number(s)
G.O. Number(s)
Chilled Water
Yes No N/A Initials
Piping Complete
Water System – flushed, filled, vented; Water treatment in place
Pumps installed and operational (rotation checked, strainers installed and cleaned)
Controls operational (3-way valves, face/bypass dampers, bypass valves, etc.)
Water system operated and tested; flow meets unit design requirements
Condenser Water
Yes No N/A Initials
Cooling tower flushed, filled, vented; Water treatment in place
Pumps installed and operational (rotation checked, strainers installed and cleaned)
Controls (3-way valves, bypass valves, etc.) operable per IM/IOM
Water system operated and flow balance to meet unit design requirements
Electrical
Yes No N/A Initials
115 volt service completed, but not connected to control panel (remote mounted starters)
Line Power Leads connected to starter; load leads(b) run from starter to compressor, ready for
connection by Service (Do not connect load leads to starter or compressor terminals).
(See Notes 1 & 4)
All interlock wiring complete and compliant with Daikin Applied specifications
Starter complies with Daikin Applied specifications
*Oil cooler solenoid wired to control panel as shown on wiring diagram
(See Notes)
Pump starter and interlocks wired
Cooling tower fans and controls wired
Wiring complies with National Electrical Code and local codes
(See Note 4)
Condenser pump starting relay (CP1,2) installed and wired
(See Note 3)
Miscellaneous
Yes No N/A Initials
*Oil cooled water piping complete. (Units with water-cooled oil coolers only)
Relief valve piping complete (per local codes)
Thermometers, wells, gauges, control, etc., installed
Minimum system load of 80% capacity available for testing/adjusting controls
Document Attached: Technical Breakdown from Daikin Tools
Document Attached: Final Order Acknowledgement
Notes: The most common problems delaying start-up and affecting unit reliability are:
1.
Field installed compressor motor power supply leads too small. Questions: Contact the local Daikin Applied sales representative. State size, number and type of
conductors and conduits installed:
a.
From Power supply to starter
b.
From starter to chiller unit (remote mounted)
2.
Centrifugal chillers with water cooled oil coolers must have a 115 volt normally closed water solenoid valve installed in the oil cooler water supply line. Daikin
Applied recommends ASCO Type 8210B27 solenoid valve or approved equal and 40-mesh strainer. Daikin Applied does not supply these components.
3.
A 115-volt field-supplied relay (CP1,2) must be used to start/stop condenser water pump on most applications. Cold condenser water must not flow through
condenser during compressor off cycle. Provisions have been made in control center for connecting CP relay, but must not have a rating in excess of 100 VA.
4.
Refer to NEC Article 430-22 (a)
*Does Not Apply to Magnetic Bearing Chillers (WMC/WME)
Contractor Representative
Signed:
Name:
Company:
Date:
Phone/Email:
Daikin
Applied
Sales Representative
Signed:
Name:
Company:
Date:
Phone/Email:
©2014 Daikin Applied
Form SF01017