Hand Over to Customer
6.1
Operational Steps
Important Points
a) The measurements taken during the test run should be recorded and kept on a test run
inspection sheet.
b) Do not forget to record the
length of the refrigerant piping
and the
refrigerant additional
charging volume
on the plate on the back of the outdoor unit external notice board, as this
information will be required for servicing the system.
c) Explain to the customer how to operate the equipment and let him try it.
d) Assemble all the relevant diagrams and other printed matter which is required to operate the
system and hand it all over to the customer (on the spot) and tell him to keep it.
e) Make the service contact address clear.
Complete test run
Make final report
(test run
inspection sheet)
Explain how to
operate
equipment
Hand over
relevant printed
materials
(V1050)
Summary of Contents for REYQ96MTJU
Page 1: ...Design Installation Testing Instruction R410A Heat Recovery 60Hz REYQ96MTJU Si39 406...
Page 6: ...Si39 406 iv Table of Contents...
Page 34: ...Installation Si39 406 28 General Information Flaring Procedure...
Page 68: ...Installation Si39 406 62 General Information Caution Caution label 3P124617 4P124614...
Page 114: ...Appendix Si39 406 108 General Information 3P135887 1...
Page 126: ...Appendix Si39 406 120 General Information 7 8 3 BS Unit BSVQ36MVJ BSVQ60MVJ 4D045338...
Page 128: ...Appendix Si39 406 122 General Information 7 9 2 Field Wiring REYQ96MTJU 3D042647A...
Page 156: ...Refrigerant Piping Si39 406 150 Installation Manual REYQ96MTJU...
Page 158: ...Refrigerant Piping Si39 406 152 Installation Manual REYQ96MTJU...
Page 230: ...Precautions for New Refrigerant R410A Si39 406 224 Precautions for New Refrigerant R410...
Page 236: ...375 Park Avenue Suite 3308 New York N Y 10152 info daikinac com www daikinac com...