SiE33-003
Hand Over to Customer
General Information
91
6. Hand Over to Customer
6.1
Operational Steps
Important Points
a) The measurements taken during the test run should be recorded and kept on a test run inspection
sheet.
b) Do not forget to record the length of the refrigerant piping and the refrigerant additional charging
volume on the plate on the back of the outdoor unit external notice board, as this information will be
required for servicing the system.
c) Explain to the customer how to operate the equipment and let him try it.
d) Assemble all the relevant diagrams and other printed matter which is required to operate the system
and hand it all over to the customer (on the spot) and tell him to keep it.
e) Make the service contact address clear.
Complete test run
Make final report
(test run
inspection sheet)
Explain how to
operate
equipment
Hand over
relevant printed
materials
(V1050)
Si33-003.book Page 91 Monday, June 25, 2001 9:06 AM
Все каталоги и инструкции здесь:
http
:
//splitoff.ru/tehn-doc.html