8 Finishing the outdoor unit installation
Installation manual
12
RXJ42+50A
R32 split series
3P512025-12X – 2021.12
f
50 Hz
220-240 V
a
b
c
d
e
a
Interconnection cable
b
Power supply cable
c
Circuit breaker
d
Residual current device
e
Power supply
f
Earth
1 2 3
3×
5
Tighten the terminal screws securely. We recommend using a
Phillips screwdriver.
6
Install the switch box cover.
8
Finishing the outdoor unit
installation
8.1
To finish the outdoor unit
installation
DANGER: RISK OF ELECTROCUTION
▪ Make sure that the system is earthed properly.
▪ Turn OFF the power supply before servicing.
▪ Install the switch box cover before turning ON the
power supply.
1
Insulate and fix the refrigerant piping and cables as follows:
g
b
a
f
e
c
d
a
Gas pipe
b
Gas pipe insulation
c
Interconnection cable
d
Field wiring (if applicable)
e
Liquid pipe
f
Liquid pipe insulation
g
Finishing tape
2
Install the service cover.
9
Configuration
9.1
Facility setting
Use this function for cooling at low outdoor temperature. This
function is designed for facilities such as equipment of computer
rooms. NEVER use in a residence or office where people occupy the
space.
9.1.1
To set the facility mode
When cutting jumper J6 on the PCB, the operation range will expand
to –15°C. The facility mode will stop if the outdoor temperature drops
below –20°C and resume when the temperature rises again.
To cut jumper J6
1
Remove the top plate of the outdoor unit.
2
Remove the front plate.
3
Remove the drip proof cover.
4
Cut jumper J6 on the outdoor unit PCB.
J6
J4
J9
J5
J7
J8
J12
d
b
c
a
a
Front plate
b
Top plate
c
Drip proof cover
d
Jumpers
INFORMATION
▪ The indoor unit may produce Intermittent noise due to
the outdoor unit fan turning ON and/or OFF.
▪ Do NOT place humidifiers or other items which might
raise humidity in rooms when you use the facility mode.
▪ Cutting jumper J6 sets the indoor unit fan to the highest
speed.
▪ Do NOT use this setting in residences or offices with
people.
10
Commissioning
NOTICE
General
commissioning
checklist.
Next
to
the
commissioning instructions in this chapter, a general
commissioning checklist is also available on the Daikin
Business Portal (authentication required).
The general commissioning checklist is complementary to
the instructions in this chapter and can be used as a
guideline and reporting template during the commissioning
and hand-over to the user.
NOTICE
ALWAYS operate the unit with thermistors and/or pressure
sensors/switches. If NOT, burning of the compressor might
be the result.