20
|
Commissioning
Installer and user reference guide
147
RYYQ+RYMQ+RXYQ
VRV IV+ heat pump
4P546228-1C – 2021.11
Internal wiring
Visually check the electrical component box and the inside of the unit for loose connections
or damaged electrical components.
Pipe size and pipe insulation
Be sure that correct pipe sizes are installed and that the insulation work is properly
executed.
Stop valves
Be sure that the stop valves are open on both liquid and gas side.
Damaged equipment
Check the inside of the unit for damaged components or squeezed pipes.
Refrigerant leak
Check the inside of the unit on refrigerant leakage. If there is a refrigerant leak, try to repair
the leak. If the repair is unsuccessful, call your local dealer. Do not touch any refrigerant
which has leaked out from refrigerant piping connections. This may result in frostbite.
Oil leak
Check the compressor for oil leakage. If there is an oil leak, try to repair the leak. If the
repairing is unsuccessful, call your local dealer.
Air inlet/outlet
Check that the air inlet and outlet of the unit is NOT obstructed by paper sheets,
cardboard, or any other material.
Additional refrigerant charge
The amount of refrigerant to be added to the unit shall be written on the included "Added
refrigerant" plate and attached to the rear side of the front cover.
Installation date and field setting
Be sure to keep record of the installation date on the sticker on the rear of the upper front
panel according to EN60335‑2‑40 and keep record of the contents of the field setting(s).
20.4 About the test run
NOTICE
Make sure to carry out the test run after the first installation. Otherwise, the
malfunction code
will be displayed on the user interface and normal operation or
individual indoor unit test run cannot be carried out.
The procedure below describes the test operation of the complete system. This
operation checks and judges following items:
▪
Check for incorrect wiring (communication check with indoor units).
▪
Check of the stop valves opening.
▪
Judgement of piping length.
▪
Gathering reference data for leak detection functionality. If the leak detection
functionality is required, the test run needs to be executed including a detailed
refrigerant situation check. If the leak detection functionality is NOT required, the
test run can skip the detailed refrigerant situation check. This can be defined by
setting [2‑88].