17
|
Piping installation
Installer and user reference guide
84
RYYQ+RYMQ+RXYQ
VRV IV+ heat pump
4P546228-1C – 2021.11
17.2.3 Multiple outdoor units: Knockout holes
Connection
Description
Front connection
Remove the front plate knockout holes to connect.
Bottom connection
Remove the knockout holes on the bottom frame and
route the piping under the bottom.
17.2.4 To route the refrigerant piping
Installation of refrigerant piping is possible as front connection or side connection
(when taken out from the bottom) as shown in the figure below.
a
b
c
a
Left-side connection
b
Front connection
c
Right-side connection
For side connections, the knockout hole on the bottom plate should be removed:
c
b
a
a
Large knockout hole
b
Drill
c
Points for drilling